Rank: Forum user
|
I was hoping that someone might be able to clarify something for me? I was always led to believe that when a temporary electric board (builders board) was installed you were required to obtain a certificate from the installing electrician. I have recently requested this from an electrician who has said that I don't need one as the markings he has made on the board, and that I don't understand, identify that it has been tested. I have had a surf around but cannot find anything definitive. Can anyone help with some guidance or direction pointing? Thanks
|
|
|
|
Rank: Super forum user
|
I have always had a proper signed and dated compliance certificate that included earthing
|
|
|
|
Rank: Super forum user
|
I agree with Bob. HSG 141 (Electrical safety on construction sites) states; “It is strongly recommended that temporary site distribution systems, new permanent distribution systems or alterations to existing systems should be tested on completion. A certificate of adequacy needs to be issued by the person carrying out the test.”
PH2
|
|
|
|
Rank: Forum user
|
Thanks, I thought that was the way forward but not having HSG 141 and not being able to download it anymore, I wanted to see what everyone else thought.
|
|
|
|
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.