Ward1427  
#1 Posted : 09 September 2014 15:54:19(UTC)
Rank: New forum user
Ward1427

I am trying to put together a HSE construction phase strategy, with specific reference to CDM and Mining regulations. Roles and Responsibilities. I would appreciate any examples or advice.
Two attempts have been submitted and rejected. I am beginning to question my own ability and or of those who are reviewing the document.
peter gotch  
#2 Posted : 10 September 2014 13:00:37(UTC)
Rank: Super forum user
peter gotch

Ward

I think it would help if you explained what the project is, including whether it includes both CDM-able construction and mine development subject to MASHAM.
Ward1427  
#3 Posted : 15 September 2014 17:21:08(UTC)
Rank: New forum user
Ward1427

The issue is the legislation for integrating both surface and underground works, i.e. the shaft sinking and the site preparation works. Naturally the sub surface works do not come under the CDM regulations therefore their is no need for a CDM'c and yet the new Mining regulations, due to become statuate next April are much more goal setting rather than the previous prescriptive mining legislation which it is replacing. Not before time, could allow us to have a similar role, yet under a different guise. My approach is that in the spirit of CDM it would make sense to continue using the CDM'c and Principal Contractor roles to ensure that we demonstrate site control for communication, and co-operation purposes.
bob youel  
#4 Posted : 17 September 2014 07:18:58(UTC)
Rank: Super forum user
bob youel

Not up to date here about the proposed changes so please provide the detail of the new proposels

There are two activities here
1: 'mining a product' which is a production activity which is not a construction activity as far as I am concerned so driving shafts in the process of extracting coal to produce a product is not a construction activity

2: Driving a shaft to allow product gathering [mining] to begin is a CDM activity in the same way as installing lighting, air con systems, railway lines etc. that will allow production to start etc. are construction activities
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.