Anybody could give advice how should look protocol for taking actions as a result of monitoring arrangements?
Regards
LK
|
|
|
|
Rank: Guest
|
Posted By Coshh Assessor
I'm not sure what you mean by a protocol? I would write a plan, that says what is wrong, who is going to do what about it and by when.
|
|
|
|
Rank: Guest
|
Posted By Ron Hunter
Perhaps a priority protocol for remedial actions required following an audit or an inspection - yes?
At its simplest then, in terms of timescale:
Category A = immediate, stop until remedied.
Category B = to be attended to within a moderate timescale (measured in days or weeks, might involve a preventative repair, arranging a toolbox talk/refresher, that sort of thing)
Category C = an action to be considered in the longer term as part of business strategy and planning, usually involving significant investment and the preparation of a business case.
You could plot a similar scale in terms of risk.
|
|
|
|
Rank: Guest
|
Posted By Lukasz
Coshh Assessor - I was not to sure what it was as well however that what Ron wrote make sense for me and it looks like good answer.
Thanks
Lukasz
|
|
|
|
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.