Rank: Super forum user
|
At what point is the lift plan required?
Should there be a lift plan for lifting equipment and or fittings using a MEWP? (Electrical/mechanical contractors).
Thanks
|
|
|
|
Rank: Super forum user
|
Chris, good question and one I have been asked numerous times on site. The answer depends on the type of load and lift. More complex and risky lifting operations will require a lift plan. Simple lifts with say a HAIB are normally executed via a generic lift plan, if at all, but once again if there is anything unusual ie unstable ground, electrical pylons, railway line etc, then a lift plan may be needed.
For MEWPS which are designed to lift people ie a cherry picker or scissor lift, there is normally no need for a lift plan because the work should be covered by a SSoW (Method Statement or similar). Equipment should only be used for what it is designed for and if it is not designed for lifting a load, for example, an excavator without an RCI and check valves, then it should not be used for lifting.
There is no legal requirement for a lift plan. LOLER Reg8 simply states lifting operations should be properly planned by a competent person...which may or may not include a lift plan designed/approved by a competent person.
Good night.
|
|
|
|
Rank: Super forum user
|
Good morning.
I've always got fitters etc to include a 'lift plan' in non-routine work where they sit down and prepare a Method Statement, and I go through it with them to ensure they take into account particular risks like collision with ceiling, pipes, light-fittings etc and that they have carefully ensured other personnel will be prevented entry to the lifting area.
JohnW
|
|
|
|
Rank: Super forum user
|
Good morning Ray, I do hope you had a good nights sleep.
Thanks for the response, just as I thought, then John comes along and says he does one every time, thank you. However I think John's 'lift plan' could be part of the method statement?
|
|
|
|
Rank: Super forum user
|
Chris
I think the key point with John's post is the reference to 'non-routine lifts' which require a lift plan. If a lift plan was included in ALL lifts then you would have to do one for say a FLT, which are normally basic lifts for an experienced FLT operator and clearly OTT. Like most things in this industry there is not a 'one size fits all' approach. The extra intervention of a lift plan should be based on the risk of the load being lifted and the surrounding environment. On a busy construction site there are many basic lifts with a FLT or Telehandler, which do not have a lift plan because it would be impractical do one each time and for each load.
|
|
|
|
Rank: Super forum user
|
If you have a number of MEWPS operating in an area I would be expecting a lifting plan of some description that would manage and co-ordinate the activities. If other lifting opeerations such as cranes are in process my preference is to include such items in the overall lifting plan for the site.
Bob
|
|
|
|
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.