Hello IOSH community.

Quick question -  a leisure centre is undergoing significant shower refurbishment and what I need to know as part of the Pre-Construction Information development - would the PCI need to include a legionella Risk Assessment?

Many thanks in advance for all replies.

Damian

Elfin Davy 09  
#2 Posted : 19 March 2019 15:51:17(UTC)
Rank: Super forum user
Elfin Davy 09

Damian

The leisure centre in question should already have a legionella risk assessment, schematics as they apply to the installation and records of regular water testing (all are legal requirements).  Would these documents not suffice for the PCI ?

thanks 1 user thanked Elfin Davy 09 for this useful post.
damian2701 on 19/03/2019(UTC)
damian2701  
#3 Posted : 19 March 2019 16:06:28(UTC)
Rank: Forum user
damian2701

Thanks for your reply, I'm mindful that the Principal Contractor must develop there Construction Phase Plan around all available information including the sigificant findings of a Legionella RA or schematics as you mention - the objective here is to provide as much info as possible to the appointed PC who may not be so proficient with such unaccustomed matters.

I'd hate for the PC to be exposed to matters relating to incidents such as Barrow -in-Furness due to a lack of info.

Damian

Dave5705  
#4 Posted : 19 March 2019 16:08:00(UTC)
Rank: Super forum user
Dave5705

If it already exists, is up to date and records are sufficient then it should do, I can't see a need to do another. Don't forget it is an ideal opportunity to check if improvements which were not reasonably practicable before could be made during the changes, and of course if changes are significant then the RA needs to be updated afterwards.

If there isn't one or it is not sufficient or current then absolutely I would say you need one before anyone disturbs anything, or you could be exposing a nightmare.

Edited by user 19 March 2019 16:13:56(UTC)  | Reason: posts crossed in post

thanks 1 user thanked Dave5705 for this useful post.
damian2701 on 19/03/2019(UTC)
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.