Welcome Guest! The IOSH forums are a free resource to both members and non-members. Login or register to use them

Postings made by forum users are personal opinions. IOSH is not responsible for the content or accuracy of any of the information contained in forum postings. Please carefully consider any advice you receive.

Notification

Icon
Error

Options
Go to last post Go to first unread
Admin  
#1 Posted : 21 February 2002 12:28:00(UTC)
Rank: Guest
Admin

Posted By Ian Mycroft I have a problem with CDM that I would like to have cleared up, if anyone can help. My organisation occasionally demolishes small structures, the work is completed within a day and the HSE are not notified. However, I have recently been told by several people, who have acted as planning supervisors and/or CDM trainers, that any demolition work requires notification. My understanding of CDM and demolition is that whilst the regulations apply to all demolition work, notification is only required if the construction phase (of which the demolition may be a part) is to be longer than 30 days or involve more than 500 person days (HSG 224 pages 5, 9 and 10). Is my interpretation of HSG 224 wrong and if so does it need to be re-written because it seems to be very clear to me?
Admin  
#2 Posted : 21 February 2002 12:52:00(UTC)
Rank: Guest
Admin

Posted By Bill Fisher Ian Demolition is notifiable. Why not go and have a chat with your local Inspector - you may be able to develop a system for the future. Regards Bill
Admin  
#3 Posted : 21 February 2002 13:10:00(UTC)
Rank: Guest
Admin

Posted By peter gotch Sorry Bill but the view that all demolition is a widespread misapprehension. Notifiability is covered by Reg 7 and is based on time not risk. The new CDM ACOP attempts to make this issue clearer. See the flow chart on page 5. Spot on Ian! Regards, Peter
Admin  
#4 Posted : 21 February 2002 13:24:00(UTC)
Rank: Guest
Admin

Posted By Jim Sweetman Ian, You appear to be receiving advice from the plethora of people who are not clear on CDM themselves. When CDM first hit the streets, I was working for a Local Authority. We were carrying out a considerable amount of demolition work, including demolishing garages (the municipal rental type). HSE viewpoint was that they didn't want to know as the work was minor and repetitive. I would advise approaching the local HSE as to what they consider to be classed as demolition. Some criteria include: 1) Are specialist contractors needed? 2) Is there a signifcant risk identified? 3) Does the work impact on the structural integrity of the structure? 4) Is a design element required? To consider it broadly, knocking down a garden wall is demolition, but it is unlikely that CDM procedures would be invoked for so minor a job. Regarding notification, I would advise looking at Figure 1 on page 5 of the recent CDM ACOP. I quote 'Will demolition or dismantling be involved? - All of the regulations apply to the work, but notification only required if regulation 7 threshhold exceeded.' In short, CDM applies to all demolition and Dismantling (as defined), but there is no need to notify unless the work is expected to take longer than 30 working days or 500 man working days. You can breathe a little now. Regards Jim Sweetman
Admin  
#5 Posted : 21 February 2002 13:56:00(UTC)
Rank: Guest
Admin

Posted By Jay Joshi I feel that there is a confusion here between the requirements of CDM & Notification to HSE and the requirements in the Building Act 1984, Section 80 to notify the local authority of the intended demolition.The former primarily deals with Health & Safety and the latter with building control.
Admin  
#6 Posted : 21 February 2002 14:05:00(UTC)
Rank: Guest
Admin

Posted By Allan St.John Holt I agree with Bill and Jim; people often get things mixed up but as they say the new ACoP gives a better explanation. One thought of interest - if you check the dangerous occurrence definitions in RIDDOR, you'll find a mention of 5 tonnes of material and I have found the HSE are happy to use this as a rough rule of thumb on quantity, risk, whatever as to what they would be interested in hearing about. Allan
Admin  
#7 Posted : 21 February 2002 15:05:00(UTC)
Rank: Guest
Admin

Posted By Zyggy Turek Ian, I agree with the latter comments that the CDM Regs.do apply to demolition work, but not notifiable unless they exceed the 30 days/500 person days criteria. To back this up I have a letter from a Principal Construction HSE Inspector which spells this out. If you e-mail me your Fax No., I will send you a copy. Zyggy.
Admin  
#8 Posted : 21 February 2002 15:53:00(UTC)
Rank: Guest
Admin

Posted By Bill Fisher Peter, Of course you are quite correct. Something done in a hurry with an a wish to emphasise the benefits in talking to HSE. Perhaps Mr Sweatman could give us a teach-in! Best regards Bill
Users browsing this topic
Guest (2)
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.