Welcome Guest! The IOSH forums are a free resource to both members and non-members. Login or register to use them

Postings made by forum users are personal opinions. IOSH is not responsible for the content or accuracy of any of the information contained in forum postings. Please carefully consider any advice you receive.

Notification

Icon
Error

Options
Go to last post Go to first unread
Admin  
#1 Posted : 08 April 2005 14:37:00(UTC)
Rank: Guest
Admin

Posted By Joel Benham The Housing Department of the Council I work for often refurbishes Council properties. Part of the work can involve taking out old window frames and doorways to communal blocks. Would this work be classified as "demolition" and therefore should it be notified under CDM? I appreciate that it may be notifiable for other reasons e.g. length of job, numbers working on site, etc. But if it were a two week job with, say, two workers on site, should it still be notified under CDM because it is demolition? I'd be most grateful for people's views.
Admin  
#2 Posted : 08 April 2005 14:48:00(UTC)
Rank: Guest
Admin

Posted By Paul Oliver Hi Joel, I work within a similar environment, i.e kitchens, windows and bathrooms and always notify under CDM. We re-furb in the region of 500 - 800 properties per year. however, the first area that caused me to notify under CDM was due the works being classed as demoliton, then there is no need to try and work out man days / hours etc. I don't see a problem with notification as our operation is pretty well run. If you want more info feel free to mail me. cheers Paul
Admin  
#3 Posted : 08 April 2005 15:03:00(UTC)
Rank: Guest
Admin

Posted By Ralph Baqar Joel, look up the thread of 28th February 2005 by Steve Mellor (currently on page 16). In summary Joel; You only need to notify when the criteria set out in reg. 7 is met. So not all demolition is notifiable. You can confirm this with the local HSE office (make sure you ask for the construction section and ask to speak to the local inspector – not one of the clerks). Regards. Ralph Baqar.
Admin  
#4 Posted : 08 April 2005 15:16:00(UTC)
Rank: Guest
Admin

Posted By Danny O'Donnell Joel, I think there may be some confusion here. CDM automatically applies to all demolition and dismantling work. However, not all demolition is notifiable. Having two guys on site for two weeks would not be notifiable in respect of any type of construction work because the Reg 7 threshold would not be exceeded. (The CDM Regs would still apply if the work involved demolition or dismantling) Also, the definition of 'Demolition' in the CDM Regs does not extend to the removal of non-structural elements, such as doors and windows. It is 'construction work' but I do not think it would be classified as demolition or dismantling, even on a grand scale. Danny
Admin  
#5 Posted : 08 April 2005 15:24:00(UTC)
Rank: Guest
Admin

Posted By Ralph Baqar Totally agree with Danny, many people get confused and presume that all demolition is notifiable (which of course it is not). Well done Danny for explaining the issue. NB. This question gets asked many times on the forum. Regards R.
Admin  
#6 Posted : 08 April 2005 15:32:00(UTC)
Rank: Guest
Admin

Posted By Roger the Dodger The fact this question and many of the RIDDOR reporting questions get asked so many times, is partly I believe, because the HSE guidance could be better worded. For example guidance is very poor as when the CDM/construction phase of a project finishes. A question I asked a few months back.
Admin  
#7 Posted : 08 April 2005 15:40:00(UTC)
Rank: Guest
Admin

Posted By Ralph Baqar I’d agree that many of the same questions surrounding CDM, CHSW and RIDDOR get asked over and over again. Maybe we should have a bank of answers that people could access?
Admin  
#8 Posted : 08 April 2005 15:43:00(UTC)
Rank: Guest
Admin

Posted By Roger the Dodger I guess there are about 30 standard health and safety questions. Once you know the standard answers that apply in most cases you could be a safety consultant........ They should have a FAQ link on this topic on the website for these very questions. Save us all a lot of time and effort, repeating ourselves
Admin  
#9 Posted : 09 April 2005 09:12:00(UTC)
Rank: Guest
Admin

Posted By steven bentham Generally I would agree with previous answers. Although the notification is surely the least painful side of what you need to comply with. There are risks at the soft strip or salvage stages prior to demolition. However, I would view that soft strip of items is part of the demolition process and this might be the time when electrics are live, absestos has not been removed etc And the recovery of salvage or historic/conservation type items might occur - sometimes less safely then the demolition! In addition structural work may take place to support adjacent structures - again is this part of the demolition works? Again you might argue on the defination of demolition does not cover any of this but an inspector might argue differently and the inspector might use other legislation for enforcement of these issues.
Admin  
#10 Posted : 09 April 2005 09:51:00(UTC)
Rank: Guest
Admin

Posted By Martyn Hendrie I think the main point many respondants have made is the fact that "demolition" in relation to the CDM regulations is NOT linked to notification of the works to the HSE. If the works are "demolition or dismantling" then there is no exemption from the application of CDM even for small works. (i.e. A Planning Supervisor must be appointed/ a safety plan prepared/ Principal Contractor appointed, etc.) Only if the demolition works are longer than 30 days construction phase or 500 person day work if less than 30 days do the HSE need to be notified. Of course all other relevant H&S legislation would still apply. The initial question was about CDM and Demolition.
Admin  
#11 Posted : 10 April 2005 21:27:00(UTC)
Rank: Guest
Admin

Posted By Lynchy Everyone 2 points: 1. I thought it was bad idea to put the notification requirements in the CDM regs in the first place since they are separate requirements - and this is what leads to the confusion of thinking that if one applies then so must the other!! ( (I recall that pre CDM notification was required anyway for projects of 6 weeks or over - is that correct or is my old brain becoming befuddled)?? 2. Our local HSE office told me ages ago that they classed demolition as a "significant part of the structure being removed" - and that's basically what we work on! Trouble is this could mean signifcant in the sense of a lot of the structure or significant in the sense of, say , a structural part of the building - makes you think doesn't it??? Lynchy
Admin  
#12 Posted : 11 April 2005 11:09:00(UTC)
Rank: Guest
Admin

Posted By ken mosley Hi Joel, The draft guidance to the new CDM regs, and the new regs themselves, shed more definitive light on the subject. In the future there there will be only two types of project ie. notifiable and non-notifiable. Some of the requirements of CDM will apply (risk reduction,competence, co-operation etc.) to non-notifiable contracts and all the requirements apply to notifiable contracts. There are prescriptive lists. On the issue of demolition the summary to the consultative document on the new CDM regs states "It is difficult to define demolition in legal terms, for example to distinguish between knocking a hole in a wall to install a new window and 'proper' demolition such as pulling down the whole or large part of a building". I suspect that you are now no wiser.
Admin  
#13 Posted : 15 April 2005 08:42:00(UTC)
Rank: Guest
Admin

Posted By Joel Benham Thank you to all of you who responded to my thread. Having reread the regulations I can see where people are coming from with their views. Most helpful!
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.