#1 Posted : 12 December 2005 11:52:00(UTC)
Rank: Guest
Admin

Posted By Vicky Godber-Ford Moore
Hello all,

I have recently been asked to carry out the planning supervisor's role on an in-house project. To do this I need a standard form of contract planning supervisors use.

Is anyone able to help me with this?

Thanks in anticipation.

Vicky
Admin  
#2 Posted : 12 December 2005 12:57:00(UTC)
Rank: Guest
Admin

Posted By Mark Gordon
Vicky

You could try the Association of Project Safety (formally Association of Planning Supervisors)www.aps.org.uk they have some standard forms for planning supervisors to use.

Regards

Mark
Admin  
#3 Posted : 12 December 2005 13:50:00(UTC)
Rank: Guest
Admin

Posted By Paul I Clark
Vicky, I have sent you an email, hope this helps.
Admin  
#4 Posted : 12 December 2005 15:14:00(UTC)
Rank: Guest
Admin

Posted By Jerry Lucey
Hi Vicky


The Royal Institute of Architects of Ireland publish a preminary safety and health plan which is useful as a template. It gives a very good outline of the risks/ areas that need to be examined.

We produce a Preliminary Safety and Health plan which is handed to the Project Supervisor Construcion Stage/ Principal Contractor. The index being as follows;

1/. General & Particular risks.
2/. PSCS/ Principal Contractor Function.
3/. Documents required from the PSCS/ Principal Contractor.
4/. Method Statements.
5/. Safety Plan/ File.
6/. Liasion with Project Supervisor Design Stage/ Planning Supervisor.
7/. Action Lists.

(Project Supervisor Design and Construction Stages are terms under Irish legislation).

The Safety File for the end user is also the responsiblity of the Planning Supervisor.

I hope this is of some help to you Vicky.

Jerry

Admin  
#5 Posted : 13 December 2005 09:00:00(UTC)
Rank: Guest
Admin

Posted By Mal Shiels
Hi Vicky, i act as a planning supervisor on many projects for small and large clients, if i can be of any help i will, just drop me a line and we can have a chat.

I can let you have a document template for your pre construction health and safety plan.

There a a lot of areas where who does what needs to be agreed early on, the word 'ensure' figures a lot in the PS duties, you need to establish who does what early on.

Good luck and as i say i am only too willing to help.

Regards, Mal
Admin  
#6 Posted : 13 December 2005 14:23:00(UTC)
Rank: Guest
Admin

Posted By Vicky Godber-Ford Moore
Thank you all for your help.

I have obtained the Form of Appointment from APS.
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.