Rank: Guest
|
Posted By Kay Sproulle I am struggling to understand how to apply CDM regs for installation of new or dismantling/removal of old machinery. The regs definitely apply, but who is the designer? Is there one at all? Removal seems the most difficult, as the removal contractors have had no involvement in deciding how/where the machinery was initially installed (or indeed designing the actual machine!), this may have happened prior to existance of CDM, and the programme of removal work may be dictated by the client. The contractor may devise the method but the host site must provide the necessary information (e.g. floor loading capacity, positions of services, weight of machines etc)and therefore is party to specifying how the work must be carried out. My head is spinning - can anyone help? Many thanks.
|
|
|
|
Rank: Guest
|
Posted By Richard Altoft see the ACOP section 110 which explains that designers include anyone specifying or designing how work is to be done and I would suggest that in removal work as in dismantling or demolition the contractor should be heavily involved in deciding how the work is done. That said they are then designers and should take account the risks to all parties in how they do that design. ACOP sections 120 to 134 might help here as well. Sections 136 and 137 give indications of what designers are not expected to do. Put more simply by involving the contractor and by the contractor considering risk in what he does everyone is moving towards best compliance with S2 and S3 of HASWA 1974 in how they safeguard selves and others. R
|
|
|
|
Rank: Guest
|
Posted By Kay Sproulle Thanks for your input. Having re-read the suggested sections some are easy to apply to machinery removal but they also imply that the client/host site plus designer of the machine and surrounding environs must be involved (which is not always possible e.g. if very old or unoccupied). It also says all designer-parties must communicate well and work as a team. With this in mind, what documentation should be produced? For a new building, there would obviously be design drawings etc. Any ideas/suggestions for the best tangible record of 'designs' for machinery removal- surely the contractor should not bear sole responsibility for said documents or for managing hazards & risks therein if he has not had complete control or been provided with sufficient, correct information? I think the pre-tender H&S plan lends itself to the above but the problem is that this should be prepared before the contractor is appointed (ACoP paragraph 150, 230) Sorry to go on but I'm intrigued in understanding CDM as best I can! Thanks again.
|
|
|
|
Rank: Guest
|
Posted By Martyn Hendrie I do not believe that developing a system of work is the same thing as a "design." Therefore a contractor deciding how to carry out a task is not necessarily a designer. I also do not think there always has to be a designer
Design is defined in Regulation 2 of the Regs as
"design in relation to any structure includes drawing, design details, specification and bill of quantities (including specification of article or substances) in relation to the structure."
If no one is doing any of these things then there is no designer.
In my experience of demolition/ machinery removal there are two groups of people that can fall under the definition of designer 1 The person who quantifies what has to be removed in a "Bill of Quantities." Often a QS, and 2 If any temporary support is required (propping, etc.) then the person that designs/specifies what is needed would be a designer.
Hope this helps
|
|
|
|
Rank: Guest
|
Posted By Ron Hunter I would suggest that,in the context of CDM or any legislation which does not apply retrospectively, you are correct in thinking that there is in fact (as far as enforcing CDM goes) no " Designer" as at the time of design there was no CDM and no Regulation 13. As Client, you will not be appointing a Designer. Similarly, you won't have a H&S File either - all pre-CDM. In 'deciding how work is to be done' you chosen Principal Contractor may well be undertaking design work, but this dual role is surely a moot point -e.g. there is no requirement to notify on an F10 who the Designer is.
It would be reasonable to research as much as possible about the existing machinery, plant and structures, trying to find records, or anyone who has undertaken similar work on similar machinery.In general terms, dismantling or demolition is usually best undertaken in the reverse order in which it was constructed, always taking into account issues such as pre-stressed members, temporary imbalance or structural weakness,release of contaminants/ pressure, conducting tests, surveys and preparatory work, etc. On this basis you also have a role to play, taking reasonable steps to locate and make avaiable existing information about the machines/plant, co-operating with the Contractor, etc. In short, there will be many competent contractors out there and your focus should be to take all reasonable steps to ensure the competency of those you engage to do this work for you.
|
|
|
|
Rank: Guest
|
Posted By Kay Sproulle Thanks for your advice, I see what you mean. (But) I'm actually asking from the point of view of a Principal Contractor who has been asked to perform the Designer role, for the removal of large machines from an unoccupied near-derelict site. It sounds like although the PC may 'design' how the work is done, he doesn't actually aqcuire any additional duties by agreeing to be designated as the 'designer'. However I was worried that in the event of a mishap on site, this agreement may give rise to the PC being blamed for failing to consider a hidden element of hazard about which no-one was able to warn him. I sincerely look forward to further input!
|
|
|
|
Rank: Guest
|
Posted By Ken Taylor Surely this situation could exist in any work situation whether CDM or not? If there is absolutely no way in which you could have been aware of a hidden hazard and did everything else safely and legally, you must have a good defence against any claim that you either were in breach of statute or were negligent in that respect. This does, however, make it important to be competent and knowledgeable and to make all the necessary enquiries, etc.
|
|
|
|
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.