Posted By B J Mann
>> The HSE, believe it or not, review all of their rules and regulations as time moves on.
I believe they do.
But historically the regulations have involved more complication, paperwork and bureaucracy (which may, or may not, be a natural, or even, to some extent, a good thing).
However, "believe it or not" they have not currently reviewed any of their rules and regulations: what they have reviewed is the Clients', and, more specifically, the Planning Supervisors', "interpretation" of them.
>> Your rants and raves smack of the retail industry (correct me if Im wrong). In fact the chances are Ive worked with you in the past.
I hope your "little rants and raves" weren't directed at moi, holyterror. And feel free to point out where I have indulged in "Any swearing".
>> If a PS is appointed late their whole involvement is pointless. How can they help 'design out' risk if the project 'starts on Monday'.
Well spotted. However, as I mentioned on the other thread I helpfully linked to: "Strangely though most of them seem to be arms of the Project Manager/ QS/ Designer for the project who, presumably, weren't "appointed late"!" Pity you hadn't spotted that.
Even more strangely the one man bands and small independent Planning Supervisors I've worked with and met try to do the best they can in the circumstances. Tailoring requirements (and costs) to the size and complexity of the job. The arms of the big consultancy practices seem to brainwash their clients into thinking there is a lot more to their role than there is, but despite that come in at the last minute and try to justify "their" role by offloading lots of paperwork onto the Principal Contractor.
>> Hence the reason you get generic, useless information. If theory jobs with short notice should be turned away but people have to eat. Hence the reason contractors start without sufficent information. They shouldn't but they do.
Stranger still, given that they don't have time to generate more than a generic pre construction plan, that they seem to have plenty of time to generate correspondence insisting the Principal Contractor should be "Providing Risk Assessments and Method Statements, etc for risks that were either insignificant or even non-existant on the project in question.". And where would they have found time to review such made-up padding if it had been generated? Did you actually do me the courtesy of reading my post before responding with your "rants and raves"?
>> Ive worked in a lot of sectors and retail, by all accounts, is terrible. Its all so fast track it should have been done yesterday. I try to avoid bad Clients now a days, especially from that sector (I can name a lot).
Feel free to explain where those clients got the idea that the Planning Supervisor arm of their consultants should post out a generic pre construction "plan" at the last minute (or later) tucked away at the back of which was the Planning Supervisors "agreements" that the Principal Contractor should generate half a forest of paperwork on non-existent or negligible construction "risks" (contrary to the old regs) and the other half of the forest on non-existent or negligible post-construction risks", buried within a load of stuff which shouldn't be in the H&S File (again, contrary to old regs)?
>> I do agree that the role of the PS has been disappointing. But under CDM so has the Client (generally don't give a **** about H&S, etc as long as the price and deadline are ok)
Again, why does the "client" insist on all the above bumf, which, eventually, directly or indirectly, he will have to waste his money on, and which, inevitably, will delay the project?
>> designer (doesn't inform Clients of duties
Thought that was the Planning Supervisors role?
>> wont design out features due to looking pretty, does it matter it is on the 20th storey)
Thought it was the Planning Supervisors role to ensure they did?
>> Principal Contractor (lots of generic paperwork which is possibly ok but demonstrates little to no knowledge of H&S practice once on site).
GI-GO
If the pre-construction plan is a pig's ear why would you expect its development to turn it into a silk purse?
>> The whole thing is a bit of a mess really. I think one of the issues is that CDM covers jobs from low value to millions and the associated paperwork should be directly proportional.
Again, that is what the old regs tell you it should be. The Principal Contractor doesn't want to go over the top. The Client wouldn't want to pay the costs of over the top paperwork. So why do we have paperwork so over the top that the HSE has had to reissue the regs in even clearer terms? Which, basically, was my original question. Which, in your own sweet way, you've gone a long way towards answering.
>> H&S Files are generally combined with O&M information as, especially on low cost/complexity projects, there is very little to put in them. It 'pads it out'.
Sigh.............
Again, the real, significant, risks, AREN'T SUPPOSED TO BE "padded out"!
Who wants them padded out?
More to the point:
WHY!
>> The PS should at the Pre Com meeting ask all the contractors what to expect and sought out what they can get. If the PS hasn't known about certain documentation it may be that its not been known about or that it is so obvious it isnt required for the File (probably is for the O&M though.
Eh?
See above.
And most of what the Planning Supervisor asks for, in my experience, can't, or shouldn't, be provided by the Principal Contractor, or, if it can, is already in the possesion of the Client, or his consultants, including the Planning Supervisor.
>> CDM's impact on shop fit projects is low but on bigger, high rise projects it is totally different. I can safely say that you wouldn't know what the PS has done because design issues have been dealt with before the contractor gets a sniff of the plans. Which is how it should be.
But I thought when you said:
>> designer (doesn't inform Clients of duties, wont design out features due to looking pretty, does it matter it is on the 20th storey)
Do try to make up your mind!
And I thought when you also said:
>> The whole thing is a bit of a mess really. I think one of the issues is that CDM covers jobs from low value to millions and the associated paperwork should be directly proportional.
You were admitting that CDM's impact on small projects was high and noticed, but not beneficially so.
Have I missed anything?
>> Any swearing you have to do please email me directly and I will give you my mobile number.
What on earth makes you think I would want to talk to you?
And I'm still waiting for you to point out where I have been swearing?
PS If you had actually bothered to read "my" "rants and raves" you might have spotted that I was paraphrasing, or even quoting what has been said here, in old HSE guidance, or even the old regs.