Posted By A.Dennis Planning to put a new vehicle door into factory, through a brick wall. Work will not exceed time limits, but will obviously involve some demolition. Will i need to notify?
|
|
|
|
|
|
Rank: Guest
|
Posted By Lee Mac How many man-hours and how long is work expected to last?
|
|
|
|
|
|
Rank: Guest
|
Posted By A.Dennis Being done in a weekend by a four man team so not more than 64 personnel hours
|
|
|
|
|
|
Rank: Guest
|
Posted By ddraigice No- not notifiable but a written plan of work for the demolition will need to be drawn up.
|
|
|
|
|
|
Rank: Guest
|
Posted By Robert K Lewis No notification so part 3 of CDM 07 does not apply. The rest however does:-)
Bob
|
|
|
|
|
|
Rank: Guest
|
Posted By Lee Mac Small scale- not notifiable- just the usual RAs, MSs and Suitably Supervised will suffice.
|
|
|
|
|
|
Rank: Guest
|
Posted By A.Dennis Thanks guys
|
|
|
|
|
|
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.