Welcome Guest! The IOSH forums are a free resource to both members and non-members. Login or register to use them

IOSH Forums are closing 

The IOSH Forums will close on 5 January 2026 as part of a move to a new, more secure online community platform.

All IOSH members will be invited to join the new platform following the launch of a new member database in the New Year. You can continue to access this website until the closure date. 

For more information, please visit the IOSH website.

Postings made by forum users are personal opinions. IOSH is not responsible for the content or accuracy of any of the information contained in forum postings. Please carefully consider any advice you receive.

Notification

Icon
Error

Options
Go to last post Go to first unread
Admin  
#1 Posted : 29 October 2007 16:21:00(UTC)
Rank: Guest
Admin

Posted By artisdeeian
Hi All.

Can anyone advise? If a construction project is concidered as one project and not several little ones, do the several little projects have to comply with CDM Regs compliance. It's just that I had a discussion in the pub last night regarding this. I thought any construction work, alterations, demolition etc had to comply with these regs?

Regrards Ian.
Admin  
#2 Posted : 29 October 2007 16:30:00(UTC)
Rank: Guest
Admin

Posted By CFT
Yes for compliance but not for notifiable, so you are essentially correct. They now owe you an extra pint!

CFT
Admin  
#3 Posted : 29 October 2007 16:38:00(UTC)
Rank: Guest
Admin

Posted By artisdeeian
Thanks CFT.

Don't think I will get the pint though.

Regards

Ian.
Admin  
#4 Posted : 30 October 2007 14:43:00(UTC)
Rank: Guest
Admin

Posted By Andrew Brown
The other point worth clarifying here is the definition of project.

I am assuming you are suggesting a scenario of splitting up a big project into lots of little projects to avoid CDM application for notification, appointment of a Prin Con and then hopefully also the old Construction regs (Now CDM 2007 part 4)?

CFT is right you cannot avoid CDM 2007 part 4 as it applies to all construction work.

But even if you decide to split the project up into lots of small ones with separate contractors for each bit it is still one project (assuming the bits run consecutively without big time gaps and are all associated with the same finished structure).

If the construction phase of the 'sub projects' lasts more than 6 weeks the whole lot is notifiable start to finish and each sub project will have to have a Principal contractor and CDM-C.

CDM 2007 Reg 2
"project" means a project which includes or is intended to include construction work and includes all planning, design, management or other work involved in a project until the end of the construction phase;

So the client would need to notify the whole project and cannot escape notification by splitting up the job into short bits. Also you cannot say the only notifiable part is the construction phase of the job.

I am involved in a major civils project due to build 2009, we are currently tendering the design and have carried out boreholes. We have notified the project to HSE, appointed a CDM-C and made the borehole contractor Prin Con for his work. The fact that he was only on site for 4 weeks is a red herring the whole project is notifiable so a PC is needed for any construction work.

The APS has printed information on this in their most recent newsletter, titled 'Ground Rules' where a member sought clarification from HSE on this issue. Unfortunately you have to be a member to access so i can't provide the link

Hope this wins next weeks bet in the pub
Admin  
#5 Posted : 30 October 2007 14:57:00(UTC)
Rank: Guest
Admin

Posted By artisdeeian
Andrew.

Thanks for this info. I remember I posted a similar question about the Client and P.C. being of the same person and his responsibilities. It pulled in about 60 + responses, it just goes to show that not everyone is conversant with these Regs and as sure as can be. I am sure the CDM regs - or should it be - "Could Do More" (CDM) regs to help us novices understand most of the new rules to help us with new projects. And sorry Yes your assumptions are correct.

Regards and many thanks

Ian.
Admin  
#6 Posted : 30 October 2007 23:29:00(UTC)
Rank: Guest
Admin

Posted By Granville Jenkins
Hi I feel that this is a good opportunity to add a bit more meat to the plate (apologies to all veggies!)

CDM 2007 brought in a new requirement for the 'client' to appoint and liaise directly with a CDM Co-ordinator for all notifiable project i.e. projects lasting more than 30 working days or more than 500 person days. It is no longer permissible for the client to delegate these duties to the Principal Contractor.

One further requirement (as mentioned in a earlier response) is that CDM now applies to all construction projects not just those that are notifiable.

Its interesting to note the wide scope which the HSE give to construction work, I have taken a section out of the CDM 2007 Regs as I feel it may be useful to other readers:-

"Construction work means the carrying out of any building, civil engineering or engineering work and includes . . . Section 2(1e)the installation, commissioning, maintenance, repair of mechanical, electrical, gas, compressed air, hydraulic, telecommunications, computer or similar services which are normally fixed within or to the structure"

Regards
Granville
Admin  
#7 Posted : 31 October 2007 09:12:00(UTC)
Rank: Guest
Admin

Posted By Robert K Lewis
Andrew

let us not forget that it is only part 3 that applies to notifiable work alone. The remaining parts apply to all construction. The effort and management cost of splitting projects often far outweighs the cost of a notifiable project. The HSE are getting pretty cute on these types of projects.

Bob
Admin  
#8 Posted : 31 October 2007 16:29:00(UTC)
Rank: Guest
Admin

Posted By Crim
I would add to the above that construction work for a domestic client is also included, however domestic clients do not have client duties under CDM 2007. (No CDM C or notification), but designers and contractors have their normal duties.

Admin  
#9 Posted : 31 October 2007 19:11:00(UTC)
Rank: Guest
Admin

Posted By Sharon
The Construction Discussion Forum

http://webcommunities.hs...m/inovem.ti/construction
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.