Posted By Peter Rees
Can anyone point me in the right direction of any commissioning checklists (for H&S) that may be available?
My dillema is this:- Have recently (4 months) ago started with new company who have been moving into a new factory. This new, purpose-built facility has 90% new process equipment, designed and built from new.
To date, very little H&S validation has been involved within the commissioning stages. We're now attempting to rectify this - hence my request.
I'm looking at something like a design/commissioning review document, or equivalent. Any ideas?
|
|
|
|
Rank: Guest
|
Posted By N Goodwin
Hi Peter,
Not sure what you mean by H&S engineering commissioning checklist but:
Firstly, if as you say, 90% of the machinery is new then you should establish if it is CE marked.
Secondly, As the end user you should carry out a PUWER inspection (reg.6) before it is put into service for the first time
|
|
|
|
Rank: Guest
|
Posted By SteveD-M
Peter
If you haven't already got it get hold of CIBSE Guide M there is a section in there about commisionaing plant. It might help.
Cheers
Steve
|
|
|
|
Rank: Guest
|
Posted By Jay Joshi
What do you mean by process plant?
The CIBSE Guide is very good for HVAC plant.
There is an IChemE guide about "Process Plant
Commissioning", 2nd Edition by David Horsley £39.50 ISBN 978 0 85295 398 3 1998, 115 pages, softback
According to the IChemE, the handbook is ideal for the non-specialist, providing advice and guidance on how to set about the problem of commissioning a new plant or a modifcation to an existing plant. The title also addresses possible problems during commissioning.
|
|
|
|
Rank: Guest
|
Posted By Mitch
Peter,
Get a copy of L22 as a starting point.
Mitch
|
|
|
|
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.