#1 Posted : 06 May 2010 14:07:34(UTC)
Rank: New forum user
PJH

If a contractor prepares an excavation (including provision of support to maintain integrity) and is contracted to reinstate excavation following completion of Third Party works, where does responsibility rest to inspect for structural integrity during the periods when others are working within excavation?

Is it with Civils Contractor with a view to maintaining integrity of their support, or with TP employer who is required to provide a safe place of work. Contract is silent on this point other than to suggest excavation works are compliant with law.

Any thoughts would be appreciated.
boblewis  
#2 Posted : 06 May 2010 18:19:27(UTC)
Rank: Super forum user
boblewis

The person undertaking the works has the responsibility to inspect the excavation throughout his works, this is actually required before the commencement of each work period not simply weekly

Bob
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.