following periodic inspection and testing of the fixed electrical systems, the company who performed the test have identified in the corrective / remedial work that further testing is required on the PI / and SI? does anyone knows what this is and whether this should have been tested as part of the initial inspection and testing? thank you
AM1  
#2 Posted : 17 June 2010 16:41:09(UTC)
Rank: Forum user
AM1

...and back to topic number 1
paul.skyrme  
#3 Posted : 17 June 2010 16:52:06(UTC)
Rank: Super forum user
paul.skyrme

AM1, Please explain a little more. The Periodic Inspection report will be limited to that agreed between the client and contractor. For example it is acceptable to only inspect & test 10% of 13A socket outlets. However, if defects are found then this frequency must be increased. However, if it has been agreed between client & contractor that no increases in inspection, thus cost will be made, then it would be acceptable to put down a code 3, further investigations required. Has the PIR been given an acceptable or unacceptable result? What do you meen by SI?
paul.skyrme  
#4 Posted : 17 June 2010 16:52:41(UTC)
Rank: Super forum user
paul.skyrme

Oh for an edit I mean mean!
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.