#1 Posted : 21 June 2010 09:47:04(UTC)
Rank: Forum user
Hector41649

I have been tasked with designing a new system of fortnightly safety audits to be conducted on various construction sites. The remit is to design a system that would show a percentage of 100. The sites have subcontractors and employed staff and are predominently Mechanical and electrically biased. Numbers vary from 10 to 100 operatives Any help would be greatly appreciated.
PhilBeale  
#2 Posted : 21 June 2010 11:46:19(UTC)
Rank: Super forum user
PhilBeale

i can't come up with a document but i would have thought one possible routes to look at following would be to come up with a list of headings for health and safety and when carrying out a tour list any issues under those headings then look at deducting the score under that one heading. Not sure if the skill set of the people on each site would make that greater difference of then qualifications or level of competence they should have for their job therefore understanding of health and safety they should be complying with or understanding. You might look at using headings like. Correct use of PPE Fire safety Welfare provisions Correct signage management procedure kept and being followed security of site Etc Etc.. I'm sure others and yourself could come up with more and possible relevant headings but as you then do a tour of the site and identify an issue you can then list it under the relevant heading than at the end of the tour you will quickly see if you have a particular issue in one or more areas. how you score the site percentage wise will depend on number of issues found and severity. You need to make sure that the more severe the issue harder the scoring will go against them. Phil
jay  
#3 Posted : 21 June 2010 12:08:46(UTC)
Rank: Super forum user
jay

You could use the "Appendix 2: Construction health and safety checklist" from HSG 150, as a basis and use the relavant parts -refer to (it is more of an inspection rather than an audit!):- http://www.hse.gov.uk/pubns/priced/hsg150.pdf
Hector41649  
#4 Posted : 21 June 2010 12:19:06(UTC)
Rank: Forum user
Hector41649

Thanks for the help.
boblewis  
#5 Posted : 21 June 2010 17:47:18(UTC)
Rank: Super forum user
boblewis

Hector You are strictly looking at a fortnightly Inspection Checksheet and NOT an audit. The best way to approach such a task is to identify the things that often go wrong or those that tend to be forgotten as unimportant. You should also be considering the items in the context of your overall H&S Objectives and the targes linked to these objectives. Another useful area for ideas is the HSE website looking at their primary concerns and campaigns relative to your work. Bob
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.