firesafety101  
#1 Posted : 01 August 2011 12:05:50(UTC)
Rank: Super forum user
firesafety101

Just a quickie - would you recommend submitting a revised F10 if a project previously notified as running for 12 months will probably extend a further 2 months?

Thanks
johnb  
#2 Posted : 01 August 2011 12:10:04(UTC)
Rank: Forum user
johnb

Chris
Yes, submit a revised F10.
If it was only going to extend by a couple of weeks I would not send in a revised F10.
Johnb
JohnW  
#3 Posted : 02 August 2011 16:25:30(UTC)
Rank: Super forum user
JohnW

Chris,

By revised F10 do you mean going on-line and changing the date (thereby retaining the project ID no.) which is what I have done?

JohnW
firesafety101  
#4 Posted : 02 August 2011 17:14:26(UTC)
Rank: Super forum user
firesafety101

I am not CDM-C but think I should tell him that the project will over run.
JohnW  
#5 Posted : 02 August 2011 17:19:35(UTC)
Rank: Super forum user
JohnW

Ah, OK Chris, yes quite right to tell CDM-C and he can update the on-line record for the project very easily.

JohnW
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.