firesafety101  
#1 Posted : 04 November 2013 16:30:07(UTC)
Rank: Super forum user
firesafety101

I've noticed quite some difference in requirements made by different CDM C's to review the RA/MS of those appointed to operate on site. While I appreciate the need to review the Initial CPP how far should the CDM C go when looking at RA/MS especially those of sub contractors?
paulw71  
#2 Posted : 04 November 2013 16:36:34(UTC)
Rank: Super forum user
paulw71

The CDMC may wish to see that these are in place and he can comment on them if he wishes however ultimatley its PC responsibility to review for suitability and if he says they are suitable then thats that. Ultimatley its not part of the CDMC role to review RA/MS`s. regards
allanwood  
#3 Posted : 04 November 2013 17:01:40(UTC)
Rank: Forum user
allanwood

This is not part of the role & function of the CDM-c, this is the PCs responsibility. If the CDM-c insists on a copy simply explain to him his duties, explain that he can have a copy by all means & point him in the direction of the documentation and the photocopier!
peter gotch  
#4 Posted : 04 November 2013 17:34:26(UTC)
Rank: Super forum user
peter gotch

Depends on the scope of CDMC appointment. I have some major projects where we are also the contract administrator and where RAMS review done by CDMC resource to advise contract administrator.
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.