Under CDM a project needs to be 30 days construction or 500 man hours, do the 30 days include weekends of just 5 working days Monday-Friday?, advise please.
|
|
|
|
Rank: Forum user
|
Hi,
Extract from ACoP - Construction (Design and Management) Regulations 2007, 'All days on which construction work takes place count towards the period of construction work. Holidays and weekends do not count if no construction work takes place on these days'.
Paul
|
|
|
|
Rank: Forum user
|
Also forgot to add for a project to be notifiable a construction project needs to last more than 30 working days or involve more than 500 person days NOT man hours !
|
|
|
|
Rank: Super forum user
|
Paragraph 16 of the ACOP answers your question and this states: “All days on which construction work takes place count towards the period of construction work. Holidays and weekends do not count if no construction work takes place on these days”.
|
|
|
|
Rank: Super forum user
|
LATCHY, Health and Safety always has the weekend off ;)
|
|
|
|
Rank: Super forum user
|
For Notification purposes, I recommend applying a pragmatic yardstick. If you expect the Construction Phase to extend over 30 days, Notify it.
Weekend working isn't always anticipated at the start, but is quite common towards the end of Projects!!
|
|
|
|
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.