#1 Posted : 25 February 2014 15:57:41(UTC)
Rank: Forum user
Tom CMIOSH

Is F10 notification just down to 2 tests? ie. 5 employees + / 500 person days?
is there a requirement that ALL demolition is notifiable - or is it just the same 2 tests as above.
Thanks.
paulw71  
#2 Posted : 25 February 2014 16:42:08(UTC)
Rank: Super forum user
paulw71

The criteria for f10 notification is as follows.

Works for a non domestic client lasting over 30 working days or 500 person days. Rquires an f10.

Demo is classed as construction works and if it meets the above criteria is notifiable.
peter gotch  
#3 Posted : 25 February 2014 17:38:56(UTC)
Rank: Super forum user
peter gotch

Lindley

From time immemorial i.e. when CDM 1994 came into force on 31 March 1995, there's been a myth that all demolition is notifiable.

But as Paul indicates notifiability is about time not risk.
firesafety101  
#4 Posted : 26 February 2014 19:12:07(UTC)
Rank: Super forum user
firesafety101

F10 is not required at all. Projects can be notified in writing not necessarily using a form F10.
Tom CMIOSH  
#5 Posted : 26 February 2014 20:04:29(UTC)
Rank: Forum user
Tom CMIOSH

Thank You
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.