Under CDM do the designers off site hours count?
|
|
|
|
Rank: Forum user
|
Count for what?
If you mean should you take them into account in determining whether a project is "Notifiable", then no.
The time limits apply to the "construction phase" of a project which is the period between the start of construction work and the completion of construction work. Design is not construction work as defined.
|
|
|
|