godscrasher  
#1 Posted : 08 October 2014 19:47:03(UTC)
Rank: Forum user
godscrasher

Big shutdown at work is coming up. An energy from waste plant is getting the superheater tubes replaced and a lot of other work in a proposed 4 week shutdown (just under 30 days).

The amount of man hours will be total over 500 hours.

I've been through all of the regs and looked at what we are doing and compared it to whether CDM apply. My answer is YES it does because we are: Going over 500 man hours, dismantling a large piece of stand alone equipment and carrying out extensive maintenance on the plant.....

Would someone be able to confirm if this is notifiable or not?

ashley.willson  
#2 Posted : 09 October 2014 07:10:14(UTC)
Rank: Guest
Guest

As far as I am concerned, yes of course CDM applies.

I think what you are actually asking is, is this a notifiable project under CDM? To which I believe it is!
ashley.willson  
#3 Posted : 09 October 2014 07:10:53(UTC)
Rank: Guest
Guest

Sorry should have read the original post better - you did ask if it was notifiable!
bob youel  
#4 Posted : 09 October 2014 09:03:51(UTC)
Rank: Super forum user
bob youel

You need to address this with the person who has commissioned the work as they may be putting the company at high risk and yes its CDM and it may be notifiable however notifiable or not the law that requires adequate management still applies

Asbestos: whilst asbestos my not be present noting the type of plant it is; it is still a consideration to be evaluated
achrn  
#5 Posted : 09 October 2014 09:22:01(UTC)
Rank: Super forum user
achrn

Godscrasher wrote:

The amount of man hours will be total over 500 hours.


It's 500 man-DAYS in the regs, not man-HOURS.
firesafety101  
#6 Posted : 09 October 2014 09:35:43(UTC)
Rank: Super forum user
firesafety101

achrn wrote:
Godscrasher wrote:

The amount of man hours will be total over 500 hours.


It's 500 man-DAYS in the regs, not man-HOURS.


Ahem ........ Please remember the Equality Act. It is "person days".

I recently had a contractor build an extension at home and he employs female decorators. He had a portaloo on site, in my front drive and I may have pulled him up for having only one toilet but when the ladies were on site there was no one else.
Betta Spenden  
#7 Posted : 09 October 2014 22:27:33(UTC)
Rank: Super forum user
Betta Spenden

FireSafety101 wrote:
achrn wrote:
Godscrasher wrote:

The amount of man hours will be total over 500 hours.


It's 500 man-DAYS in the regs, not man-HOURS.


Ahem ........ Please remember the Equality Act. It is "person days".

I recently had a contractor build an extension at home and he employs female decorators. He had a portaloo on site, in my front drive and I may have pulled him up for having only one toilet but when the ladies were on site there was no one else.


If he got two on site then more the fool him for paying for things that are not always required.
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.