Frank1970  
#1 Posted : 28 April 2015 16:04:20(UTC)
Rank: Forum user
Frank1970

Hi, I'm assisting one of my clients as CDM-C / Principal Designer for a house building project. In order to establish my own fees I am trying to get an understanding as to how much (as a percentage) a client would typically allocate for the planning, managing, monitoring and co-ordinating of health and safety in the pre-construction phase of a project. Is there a general rule of thumb that a client would work to, e.g. say I will allocate 10% of the value of a £1,000,000 project for health and safety? Many thanks!
firesafety101  
#2 Posted : 28 April 2015 18:45:07(UTC)
Rank: Super forum user
firesafety101

I am not a client but you can search the interweb for fees charged by the various duty holders.
paulw71  
#3 Posted : 29 April 2015 09:33:20(UTC)
Rank: Super forum user
paulw71

Frank1970 wrote:
Hi, I'm assisting one of my clients as CDM-C / Principal Designer for a house building project. In order to establish my own fees I am trying to get an understanding as to how much (as a percentage) a client would typically allocate for the planning, managing, monitoring and co-ordinating of health and safety in the pre-construction phase of a project. Is there a general rule of thumb that a client would work to, e.g. say I will allocate 10% of the value of a £1,000,000 project for health and safety? Many thanks!
If you manage to get your client to spend 10% of project value on health and safety then you are in the wrong career and your unrivalled negotiating talents would be put to a much better use in the United Nations. Regards
kenty  
#4 Posted : 29 April 2015 10:05:42(UTC)
Rank: Forum user
kenty

We are typically seeing prelims set around the 6-8% range, which includes the management of H&S throughout the projects, in addition to the general site management.
Ron Hunter  
#5 Posted : 29 April 2015 13:17:41(UTC)
Rank: Super forum user
Ron Hunter

I think it unwise to attempt to consider the CDM/Principal Designer roles as interchangeable in terms of costs/fees. There's a world of difference between "coordinating" (in the often woolly contextual interpretation of CDM2007 Regulation 20, where CDM-C fees for the type of Project you describe could be typically less that 1%) and being the person in charge of the pre-construction phase. (Regs 5(1); 11 and 12 of CDM2015.
Frank1970  
#6 Posted : 30 April 2015 12:04:55(UTC)
Rank: Forum user
Frank1970

Most useful, thank you everyone. You understand of course that the 10% was hypothetical. I found this link quite useful: http://www.sitesage.co.uk/health_fees.html
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.