Hi,
I am looking for some for some help on this please - legal extract is below:
Every employer shall ensure that, where the safety of lifting equipment
depends on the installation conditions, it is thoroughly examined
The issue for me hinges on the words 'installation conditions' - would you say the safety of lifting equipment which was put together (built) on site is dependant on the installation conditions?
Our supplier is adamant that the CE Certificate of conformity will do, as its new equipment, however, I remain concern about when installation conditions should be considered.
Is there a crane expert out there who could share the benefit of their experience pleases?
|
|
|
|
Rank: Super forum user
|
That very much depends on the type of crane. The floor strength for a swing jib for example is definitely an "installation condition" as if the floor concrete does not have steel work and sufficient concrete strength (upwards of C30), then the load on the end of the crane can pull the pillar out of the ground.
A frames or overhead travelling cranes are less susceptible to this but you still need good anchoring points to ensure that the weight on one extension does not overbalance the whole.
A Certificate of Conformity is not enough anyway, you need a test certificate under LOLER for all lifting equipment to prove that it can take the load.
|
|
|
|
Rank: New forum user
|
It is a straddle carrier mobile crane unit.
I was expecting to receive the LOLER Cert, but the legislation inserted below seems to indicate this is not required unless the installation conditions apply:(1) Every employer shall ensure that before lifting equipment is put into
service for the first time by him it is thoroughly examined for any defect unless
either –
(a) the lifting equipment has not been used before; and
(b) in the case of lifting equipment for which an EC declaration of conformity
could or (in the case of a declaration under the Lifts Regulations 1997)
should have been drawn up, the employer has received such declaration
made not more than 12 months before the lifting equipment is put into
service;
This is why the question of Installation conditions are so important
Thanks for your help
|
|
|
|
Rank: Super forum user
|
I think the issue is that this is a mobile unit and therefore, not installed.
"158 Regulation 6 applies to both permanently installed and mobile lifting equipment
although different measures should be taken in each case to control the risks.
‘Installed’ refers only to lifting equipment which is assembled at a particular location
and not to mobile lifting equipment which is ‘positioned’ in a particular location to
carry out lifting operations."
Trust this answers your queries. the Declaration of Conformity should suffice.
|
|
|
|
IOSH forums home
»
Our public forums
»
OSH discussion forum
»
The definition of 'Installation conditions in LOLER'
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.