H I am assuming that, considering the 30 day and 20 person rule (or 500 man days) that if we are asked to carry out building specifications (asbestos removal) then we become a Designer? Or we becoming a Principal Designer if nominated by the Client?
RayRapp  
#2 Posted : 07 October 2015 12:26:46(UTC)
Rank: Super forum user
RayRapp

Sorry but your question makes no sense - can you re-phrase it if you want a proper answer.
Kate  
#3 Posted : 07 October 2015 12:33:15(UTC)
Rank: Super forum user
Kate

The role of Designer and the need to appoint a Principal Designer are not related to whether the project is notifiable. I'd guess that's why Ray says your question makes no sense.
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.