Rank: Forum user
|
As an H&S file is not required for a project that has only 1 contractor, what is the purpose of a Health and Safety File? Why is a file only required where 2 or more contractors are on a project?
This question was asked during a seminar with a wide range of opinions and answers being given. I would be interested in the thoughts of board members with regard to this subject taking into account
Appendix 4 (3) of CDM 2015 that states;
"The file must contain information about the current project likely to be needed to
ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file,
information on the following should be considered for inclusion:
(a) a brief description of the work carried out;
(b) any hazards that have not been eliminated through the design and
construction processes, and how they have been addressed (eg surveys or
other information concerning asbestos or contaminated land);
(c) key structural principles (eg bracing, sources of substantial stored energy –
including pre- or post-tensioned members) and safe working loads for floors
and roofs;
(d) hazardous materials used (eg lead paints and special coatings);
(e) information regarding the removal or dismantling of installed plant and
equipment (eg any special arrangements for lifting such equipment);
(f) health and safety information about equipment provided for cleaning or
maintaining the structure;
(g) the nature, location and markings of significant services, including
underground cables; gas supply equipment; fire-fighting services etc;
(h) information and as-built drawings of the building, its plant and equipment (eg
the means of safe access to and from service voids and fire doors)."
|
|
|
|
Rank: Super forum user
|
L153, on page 81 it says
Quote:
Contractor
16 The contractor has no specific duties placed on them in relation to the health and safety file.
So they seem to have extended this to a one-contractor project.
But there are surely situations where a one contractor has done a variety of work where the client should get an H&S file.
An example: a contractor installs a large boiler, there's a control box, exhaust ducting, a CO monitor, water plumbing, gas connections, electrics, some structural change was made to support the boiler, instruction manual with servicing guidance.
|
|
|
|
Rank: Forum user
|
JohnW wrote:L153, on page 81 it says
Quote:
Contractor
16 The contractor has no specific duties placed on them in relation to the health and safety file.
So they seem to have extended this to a one-contractor project.
But there are surely situations where a one contractor has done a variety of work where the client should get an H&S file.
An example: a contractor installs a large boiler, there's a control box, exhaust ducting, a CO monitor, water plumbing, gas connections, electrics, some structural change was made to support the boiler, instruction manual with servicing guidance.
What non-construction people struggled with is that the file is put together for future use. With 1 contractor, potentially doing lots of different work a file is not needed, hence persons doing future work have no file to view! The hazards/risks for future work are the same whether there is 1 contractor or 2.
|
|
|
|
Rank: Super forum user
|
This is an odyssey and I suspect a compromise. My guess is that the HSE has taken the line that most single contractor projects are either very small or involve the installation of machinery where there is an obligation to provide a technical file under other legislation. Those that are not will be very small in number and they will tackle issues when they arise.
|
|
|
|
Rank: Super forum user
|
Colossians 1:14 wrote:As an H&S file is not required for a project that has only 1 contractor, what is the purpose of a Health and Safety File? Why is a file only required where 2 or more contractors are on a project?
This question was asked during a seminar with a wide range of opinions and answers being given. I would be interested in the thoughts of board members with regard to this subject taking into account
Appendix 4 (3) of CDM 2015 that states;
"The file must contain information about the current project likely to be needed to
ensure health and safety during any subsequent work, such as maintenance,
cleaning, refurbishment or demolition. When preparing the health and safety file,
information on the following should be considered for inclusion:
(a) a brief description of the work carried out;
(b) any hazards that have not been eliminated through the design and
construction processes, and how they have been addressed (eg surveys or
other information concerning asbestos or contaminated land);
(c) key structural principles (eg bracing, sources of substantial stored energy –
including pre- or post-tensioned members) and safe working loads for floors
and roofs;
(d) hazardous materials used (eg lead paints and special coatings);
(e) information regarding the removal or dismantling of installed plant and
equipment (eg any special arrangements for lifting such equipment);
(f) health and safety information about equipment provided for cleaning or
maintaining the structure;
(g) the nature, location and markings of significant services, including
underground cables; gas supply equipment; fire-fighting services etc;
(h) information and as-built drawings of the building, its plant and equipment (eg
the means of safe access to and from service voids and fire doors)."
First, I must point out the CDM 2015 Regulations do not prescribe a H&S File must be provided where there is more than one contractor. However L153 Guidance states - 'The health and safety file is only required for projects involving more than one contractor.' I suspect this was an after-thought by the HSE. Another anomaly with the regulations!
Where there is only one contractor there may still be a need for a H&S File. What exactly is provided depends largely on the requirements of the client. I have been invloved in large projects where the client insisted all and sundry was included in the H&S File, including RAMS.
For many projects such as basic building, repairs and mainteance work a H&S File will not be needed, regardless of whether there is more than one contractor involved. The regulations do not explicitly provide for this scenario, however common sense prevails...a lot of common sense is needed with regards to CDM 2015 in my opinion.
|
|
|
|
Rank: Super forum user
|
RayRapp wrote:
First, I must point out the CDM 2015 Regulations do not prescribe a H&S File must be provided where there is more than one contractor.
Yes they do.
Regulation 5(1) requires that where there is more than one contractor, or if it is reasonably foreseeable that more than one contractor will be working on a project at any time, the client must appoint a principal designer.
Regulation 12(5) requires that every principal designer must prepare a health and safety
file appropriate to the characteristics of the project which must contain information relating to
the project.
So the regulations require that there be a health and safety file for every project with more than one contractor, because every such project will have a PD, and every PD must prepare such a file.
|
|
|
|
Rank: Super forum user
|
Health and Safety Files should be maintained for the lifetime of the structure. CDM requirement has been around since 1994. Any Client who doesn't have at least the rudiments of a H&S File after 20+ years of statutory requirement should be asking questions.
Why does CDM only require the File to be considered where there is more than one contractor? (and that is a prescriptive requirement)
Because that's exactly what the Parent Directive states, and the regulator was constrained by perceived "gold plating" issues.
Do note that Regulation 9 requires every Designer to consider matters required for the File. Otherwise, I suggest the pragmatic approach would be for the Client to ask via contract (or preconstruction information pack) for what he wants.
New Builds: Can you really build something from the ground up with only one contractor? I doubt it.
|
|
|
|
Rank: Super forum user
|
achrn wrote:RayRapp wrote:
First, I must point out the CDM 2015 Regulations do not prescribe a H&S File must be provided where there is more than one contractor.
Yes they do.
Regulation 5(1) requires that where there is more than one contractor, or if it is reasonably foreseeable that more than one contractor will be working on a project at any time, the client must appoint a principal designer.
Regulation 12(5) requires that every principal designer must prepare a health and safety
file appropriate to the characteristics of the project which must contain information relating to
the project.
So the regulations require that there be a health and safety file for every project with more than one contractor, because every such project will have a PD, and every PD must prepare such a file.
Oh no they don't.
It is implied via regulations 5(1) and 12(5) but nowhere in the regulations does it state that a H&S File must be provided where there is more than one contractor...and that's what I wrote.
|
|
|
|
Rank: Super forum user
|
RayRapp wrote:
It is implied via regulations 5(1) and 12(5) but nowhere in the regulations does it state that a H&S File must be provided where there is more than one contractor...and that's what I wrote.
If there is no safety file, regulation 5(1) or 12(5) has not been complied with. The regulations require a health and safety file for projects with more than one contractor. This isn't an implicit requirement, this is explicit - those regulations can only be satisfied if a file is created.
|
|
|
|
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.