fiesta  
#1 Posted : 16 November 2016 16:26:11(UTC)
Rank: Forum user
fiesta

Hello All,

I was wondering if anyones knows any examples of sucessful prosecutions of construction companies where excessive working hours on site have been a factor in an acident. Or, where exccessive hours worked by agency / sub-contracted staff have been seen as an unacceptable way of avoiding the EU Working Time Directive. I have tried several google serches but come up with nothing.

Thanks

Andy

RayRapp  
#2 Posted : 17 November 2016 11:39:49(UTC)
Rank: Super forum user
RayRapp

Hi Andy The only case I can think of is where an employee had a road accident after working excessive hours and was permitted to drive home by his employer - citation escapes me. Of course, there may be future cases, but linking excessive hours directly with an accident is problematic in itself because there could be a number of causal factors in construction site accident. The HSE guidance Indg 382 may be worth a read. http://www.hse.gov.uk/pubns/indg382.pdf
bob youel  
#3 Posted : 21 November 2016 11:27:14(UTC)
Rank: Super forum user
bob youel

Hi

what do U mean by 'excessive' hours?

peter gotch  
#4 Posted : 21 November 2016 13:46:49(UTC)
Rank: Super forum user
peter gotch

Frank Field Chair of the Commons Work and Pensions Committee has asked HSE to investigate Hermes couriers who are being asked to work 7 days a week in the run up to Christmas. Some couriers could end up working 20 successive days. HSE is "considering his request".

fiesta  
#5 Posted : 22 November 2016 14:41:51(UTC)
Rank: Forum user
fiesta

Thanks for your resposnes.

Bob, what constitutes "Excessive" is part of my problem.

We do have some sub-contracted operatives working long hours on site, on a number of sucessive days. A timesheet came across my desk after an labour agency queried the validity of the claimed hours, i.e. 20,19,20,20, for 4 consecutive days. To my mind this is excessive, and dangerous.

In an attempt to educate Site Managers and Contract Managers of the risks involved in this I was hoping there might be some guidance.

Andy

A Kurdziel  
#6 Posted : 22 November 2016 14:58:56(UTC)
Rank: Super forum user
A Kurdziel

Originally Posted by: fiesta Go to Quoted Post

Thanks for your resposnes.

Bob, what constitutes "Excessive" is part of my problem.

We do have some sub-contracted operatives working long hours on site, on a number of sucessive days. A timesheet came across my desk after an labour agency queried the validity of the claimed hours, i.e. 20,19,20,20, for 4 consecutive days. To my mind this is excessive, and dangerous.

In an attempt to educate Site Managers and Contract Managers of the risks involved in this I was hoping there might be some guidance.

Andy

How does that work with the requirement for an 11 hour break every 24 hours ?

Users browsing this topic
Guest (3)
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.