#1 Posted : 16 May 2018 10:52:14(UTC)
Rank: New forum user
kmorrow87

Hi all Just wanted to reassure myself - am I correct in thinking that the AP that done the lift plan is only required to be on site during the lift if it is not a simple lift? Where it is a simple lift, it can be overseen by the lift supervisor in conjunction with the lift plan carried out by the AP? Thanks
thanks 1 user thanked kmorrow87 for this useful post.
Kim Hedges on 04/06/2018(UTC)
Blackburn31728  
#2 Posted : 16 May 2018 11:37:47(UTC)
Rank: Forum user
Blackburn31728

He does not have to be one site for Basic lifts you are correct

Woolf13  
#3 Posted : 16 May 2018 11:47:14(UTC)
Rank: Forum user
Woolf13

Without going through all the duties etc. the complexity of a lifting operation depends on the hazards associated with the load path, the load itself and the equipment lifting it, and the environment in which the lifting operation is being carried out. 

The duties of an appointed person for crane operations can vary according to the complexity of the operation. The duties for a basic lift are considerably fewer and less demanding than for a complex lift. An appointed person employed for a basic lift might not be competent to carry out a more complicated operation, and another appointment could be required for this.

Basic Lift

The appointed person may make an assessment on the basis of information with which they have been provided, visit the site personally or delegate a competent person to undertake the visit on their behalf.

Intermediate Lift

The appointed person may visit the site personally or delegate a competent person to undertake the visit on their behalf.

Complex Lift

Being present on the site during a complex lift.

I hope this helps.

kmorrow87  
#4 Posted : 16 May 2018 11:56:57(UTC)
Rank: New forum user
kmorrow87

Great!- thanks for your responses
Kim Hedges  
#5 Posted : 04 June 2018 21:49:34(UTC)
Rank: Super forum user
Kim Hedges

Added to this post, note, if the lift changes from the original lifting plan, (it happens) then the A.P. needs to adapt or change the lifting plan.  That's why the A.P. get more money than the Lift Supervisor - or so I've been informed (I am a CPCS Slinger Banksman). 

Users browsing this topic
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.