#1 Posted : 20 August 2018 05:00:12(UTC)
Rank: Forum user
parvezsafety

Dear sir,

After prtoviding controle measure  what will reduce in RAM ( Risk assesent matrix) .

Likelihood  or  Severity

Blackburn31728  
#2 Posted : 20 August 2018 06:10:51(UTC)
Rank: Forum user
Blackburn31728

The severity will usally stay the same and is unlikley to change were as the likiehood will reduce due to the control measures you put in hope this helps but it is simple risk management

George_Young  
#3 Posted : 20 August 2018 06:11:07(UTC)
Rank: Super forum user
George_Young

Originally Posted by: parvezsafety Go to Quoted Post

Dear sir,

After prtoviding controle measure  what will reduce in RAM ( Risk assesent matrix) .

Likelihood  or  Severity

Both can reduce, but that will depend on the control measures put in place.

Steve e ashton  
#4 Posted : 20 August 2018 06:14:58(UTC)
Rank: Super forum user
Steve e ashton

It depends..... It depends on how you have defined/stated the risk, It depends on what your control measure(s) is/are. So if you think the risk is chemical burns on the skin and you substitute a less corrosive chemical, the severity will reduce (to chemical irritation of the skin perhaps...) If you think the risk is chemicals on the skin and you provide gloves, then the likelihood will reduce. (But severity will remain the same) This topic has been discussed many times over the years... Try doing a search on previous threads...
A Kurdziel  
#5 Posted : 20 August 2018 08:43:38(UTC)
Rank: Super forum user
A Kurdziel

As said the best way to reduce the risk is by eliminating the hazard. If you can’t do that you reduce the likelihood of it causing (manifesting?) harm.

thanks 1 user thanked A Kurdziel for this useful post.
parvezsafety on 31/08/2018(UTC)
Waz  
#6 Posted : 20 August 2018 13:24:13(UTC)
Rank: Forum user
Waz

The point of conducting a risk assessment is to reduce the likelihood of harm being realised.  Therefore, you would look to reduce the likelihood.  In exceptional circumstances, the controls to be implemented may also reduce the severity e.g. use of 110V or less tooling (110V can't kill you, but 230V+ can), but this is rare.  

You may think controls would reduce the severity, but if they were to fail, the consequence would be the same, therefore, I recognise there to be few circumstances whereby Severity reduces.

thanks 1 user thanked Waz for this useful post.
parvezsafety on 31/08/2018(UTC)
Users browsing this topic
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.