Evans38004  
#1 Posted : 21 January 2013 13:18:47(UTC)
Rank: Forum user
Evans38004

We intend upgrading one of our buildings. The actual dismantling of current building and replacement will take place next year (start April 2014) and is expected to last 4 to 5 months - I know that this makes it a notifiable CDM project, In a few weeks time we need to ascertain the geology of the area we are intending to bring in experts to dig trial holes - this part of the project will last 1 week max. Do I need to raise the F10 now before the trial hole work for the whole project? or are they distinctly different enough to warrant only the main project next year to be notifiable?
DNW  
#2 Posted : 21 January 2013 15:20:57(UTC)
Rank: Forum user
DNW

I would suggest that would be considered survey/enabling work so not part of the construction phase - not notifiable DNW
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.