Welcome Guest! The IOSH forums are a free resource to both members and non-members. Login or register to use them

Postings made by forum users are personal opinions. IOSH is not responsible for the content or accuracy of any of the information contained in forum postings. Please carefully consider any advice you receive.

Notification

Icon
Error

Options
Go to last post Go to first unread
jarsmith83  
#1 Posted : 15 December 2014 19:20:08(UTC)
Rank: Super forum user
jarsmith83

To what extent does the following excerpt apply? Definitions Construction work 13 Construction work is defined in the Regulations. The following are not construction work as defined: (a) (b) putting up and taking down marquees and similar tents designed to be re-erected at various locations; general maintenance of fixed plant, except when this is done as part of other construction work, or it involves substantial dismantling or alteration of fixed plant which is large enough to be a structure in its own right, for example structural alteration of a large silo; complex chemical plant; power station generator or large boiler; We carry out general maintenanice activity to M&E equipment such as servicing boilers, perhaps runninget new cables, changing belts, water treatment. I understand these are all maintenance activities, but feel it's an extreme description to name this type of work construction work, but obviously want to work to the letter of the law.
ashleywillson  
#2 Posted : 16 December 2014 07:15:38(UTC)
Rank: Super forum user
ashleywillson

“construction work” means the carrying out of any building, civil engineering or engineering construction work and includes— (a)the construction, alteration, conversion, fitting out, commissioning, renovation, repair, upkeep, redecoration or other maintenance (including cleaning which involves the use of water or an abrasive at high pressure or the use of corrosive or toxic substances), de-commissioning, demolition or dismantling of a structure; (b)the preparation for an intended structure, including site clearance, exploration, investigation (but not site survey) and excavation, and the clearance or preparation of the site or structure for use or occupation at its conclusion; (c)the assembly on site of prefabricated elements to form a structure or the disassembly on site of prefabricated elements which, immediately before such disassembly, formed a structure; (d)the removal of a structure or of any product or waste resulting from demolition or dismantling of a structure or from disassembly of prefabricated elements which immediately before such disassembly formed such a structure; and (e)the installation, commissioning, maintenance, repair or removal of mechanical, electrical, gas, compressed air, hydraulic, telecommunications, computer or similar services which are normally fixed within or to a structure, Reference part e specifically. So yes CDM does apply. However... I suspect that your work is not likely to take 30+ days or 500+ man hours so will not be notifiable to the HSE. Hope that helps.
bob youel  
#3 Posted : 16 December 2014 08:38:13(UTC)
Rank: Super forum user
bob youel

Does it really matter if it is CDM or it is not CDM as U need an adequate management system in all cases?
paulw71  
#4 Posted : 16 December 2014 09:32:31(UTC)
Rank: Super forum user
paulw71

ashleywillson wrote:
“construction work” means the carrying out of any building, civil engineering or engineering construction work and includes— (a)the construction, alteration, conversion, fitting out, commissioning, renovation, repair, upkeep, redecoration or other maintenance (including cleaning which involves the use of water or an abrasive at high pressure or the use of corrosive or toxic substances), de-commissioning, demolition or dismantling of a structure; (b)the preparation for an intended structure, including site clearance, exploration, investigation (but not site survey) and excavation, and the clearance or preparation of the site or structure for use or occupation at its conclusion; (c)the assembly on site of prefabricated elements to form a structure or the disassembly on site of prefabricated elements which, immediately before such disassembly, formed a structure; (d)the removal of a structure or of any product or waste resulting from demolition or dismantling of a structure or from disassembly of prefabricated elements which immediately before such disassembly formed such a structure; and (e)the installation, commissioning, maintenance, repair or removal of mechanical, electrical, gas, compressed air, hydraulic, telecommunications, computer or similar services which are normally fixed within or to a structure, Reference part e specifically. So yes CDM does apply. However... I suspect that your work is not likely to take 30+ days or 500+ man hours so will not be notifiable to the HSE. Hope that helps.
500 plus man hours ? If your going to offer advice to people at least make sure its correct.
jarsmith83  
#5 Posted : 16 December 2014 13:34:40(UTC)
Rank: Super forum user
jarsmith83

bob youel wrote:
Does it really matter if it is CDM or it is not CDM as U need an adequate management system in all cases?
Yes it does matter otherwise I would not have asked the question.
jarsmith83  
#6 Posted : 16 December 2014 13:36:19(UTC)
Rank: Super forum user
jarsmith83

paulw71 wrote:
ashleywillson wrote:
“construction work” means the carrying out of any building, civil engineering or engineering construction work and includes— (a)the construction, alteration, conversion, fitting out, commissioning, renovation, repair, upkeep, redecoration or other maintenance (including cleaning which involves the use of water or an abrasive at high pressure or the use of corrosive or toxic substances), de-commissioning, demolition or dismantling of a structure; (b)the preparation for an intended structure, including site clearance, exploration, investigation (but not site survey) and excavation, and the clearance or preparation of the site or structure for use or occupation at its conclusion; (c)the assembly on site of prefabricated elements to form a structure or the disassembly on site of prefabricated elements which, immediately before such disassembly, formed a structure; (d)the removal of a structure or of any product or waste resulting from demolition or dismantling of a structure or from disassembly of prefabricated elements which immediately before such disassembly formed such a structure; and (e)the installation, commissioning, maintenance, repair or removal of mechanical, electrical, gas, compressed air, hydraulic, telecommunications, computer or similar services which are normally fixed within or to a structure, Reference part e specifically. So yes CDM does apply. However... I suspect that your work is not likely to take 30+ days or 500+ man hours so will not be notifiable to the HSE. Hope that helps.
500 plus man hours ? If your going to offer advice to people at least make sure its correct.
Person days, yes understood.
jay  
#7 Posted : 16 December 2014 15:03:48(UTC)
Rank: Super forum user
jay

Jarsmith, It appears that you have copied the text of the CDM ACoP on page 8, i.e. where it clarifies from the definition in the text of the regulations what does NOT constitute construction work. However, the Management Regulations & PUWER will apply Therefore general maintanance as described by you is unlikely to be construction work. Paragraph 13-Definitions-Construction work Construction work is defined in the Regulations. The following are not construction work as defined: (a) putting up and taking down marquees and similar tents designed to be re-erected at various locations; (b) general maintenance of fixed plant, except when this is done as part of other construction work, or it involves substantial dismantling or alteration of fixed plant which is large enough to be a structure in its own right, for example structural alteration of a large silo; complex chemical plant; power station generator or large boiler; c) tree planting and general horticultural work; (d) positioning and removal of lightweight movable partitions, such as those used to divide open-plan offices or to create exhibition stands and displays; (e) surveying – this includes taking levels, making measurements and examining a structure for faults; (f) work to or on vessels such as ships and mobile offshore installations; (g) off-site manufacture of items for later use in construction work (for example roof trusses, pre-cast concrete panels, bathroom pods and similar prefabricated elements and components); (h) fabrication of elements which will form parts of offshore installations; (i) the construction of fixed offshore oil and gas installations at the place where they will be used. Paragraph 14 Some construction projects include operations, such as those described in the previous paragraph, which are not themselves construction work. Where this is the case, the overlap between the construction and non-construction work should be addressed in the management arrangements and the construction phase plan.
paulw71  
#8 Posted : 16 December 2014 15:19:24(UTC)
Rank: Super forum user
paulw71

Thats what he said isnt it ?
ashleywillson  
#9 Posted : 16 December 2014 15:26:09(UTC)
Rank: Super forum user
ashleywillson

Wow Paul, personally I think you need to consider the perception you are giving off when speaking to others.... I made a small typo which I think Jarsmith realised and I do apologise for that mistake. I think you would do well to remember that we are all on the same side here and your response to my mistake was less than helpful. Just some feedback which you might like to think on....maybe.
paulw71  
#10 Posted : 16 December 2014 15:32:48(UTC)
Rank: Super forum user
paulw71

Ashley Thanks for the feedback. Heres some for you. Spelling mistakes are typos. Getting hours and weeks mixed up are errors. If you are providing people with advice you would do well to be sure of what your talking about.
jay  
#11 Posted : 16 December 2014 15:38:27(UTC)
Rank: Super forum user
jay

paulw71 wrote:
Thats what he said isnt it ?
He was not clear in his posting that the information, i.e what he said was from the ACoP.
ashleywillson  
#12 Posted : 16 December 2014 15:40:55(UTC)
Rank: Super forum user
ashleywillson

Glad to see that you have taken the feedback on board.... I apologise for the ERROR that I made. It is not that I didn't know rather that I typed it without thinking. Believe you me, I am very sure of what I am talking about. Obviously we can't all be perfect in the things we do and say now can we? Although given your spate of posts on here I guess I am wrong on this too....
achrn  
#13 Posted : 16 December 2014 15:43:53(UTC)
Rank: Super forum user
achrn

paulw71 wrote:
Ashley Thanks for the feedback. Heres some for you. Spelling mistakes are typos. Getting hours and weeks mixed up are errors. If you are providing people with advice you would do well to be sure of what your talking about.
Errm, I wouldn't want to intrude into this happy exchange, but he didn't get hours and weeks mixed up, did he. Will you be lambasting yourself for the grievous error of getting days and weeks mixed up now?
paulw71  
#14 Posted : 16 December 2014 15:46:57(UTC)
Rank: Super forum user
paulw71

achrn wrote:
paulw71 wrote:
Ashley Thanks for the feedback. Heres some for you. Spelling mistakes are typos. Getting hours and weeks mixed up are errors. If you are providing people with advice you would do well to be sure of what your talking about.
Errm, I wouldn't want to intrude into this happy exchange, but he didn't get hours and weeks mixed up, did he. Will you be lambasting yourself for the grievous error of getting days and weeks mixed up now?
Yes. I was sincerely hoping that no-one would notice that. Still now you have I fear I must stand and take whats coming.
ashleywillson  
#15 Posted : 16 December 2014 15:47:54(UTC)
Rank: Super forum user
ashleywillson

Nothing coming from me, Paul. As I said, we all make mistakes....
paulw71  
#16 Posted : 16 December 2014 15:48:50(UTC)
Rank: Super forum user
paulw71

And yes an apology is in order. Ashley I apologise.
ashleywillson  
#17 Posted : 16 December 2014 15:51:21(UTC)
Rank: Super forum user
ashleywillson

Accepted, and likewise I apologise to you if I got your back up.
paulw71  
#18 Posted : 16 December 2014 15:55:49(UTC)
Rank: Super forum user
paulw71

Thank you. Your very gracious. Christmas just gets to me.
RayRapp  
#19 Posted : 16 December 2014 16:05:33(UTC)
Rank: Super forum user
RayRapp

...and all lived happily ever after - LOL.
Xavier123  
#20 Posted : 16 December 2014 16:46:25(UTC)
Rank: Super forum user
Xavier123

God bless us. Everyone. Back on topic, the mention of maintenance within both what IS and what IS NOT construction work is a little confusing. Never given it that much thought till now. First thoughts on reading through the ACoP and the Regs are thus: The key difference appears to be that which is being maintained. Structures and 'services' being maintained seem likely to fall under construction work. Fixed plant does not except in certain circumstances. The services bit seems vague since it includes mechanical, electrical, gas, etc. which makes me wonder what elements of 'fixed plant' they were trying to exclude within the ACoP...? I suspect the services bit thus relates to pipes, cabling etc. Am I getting that right? If so, following that logic might suggest that some of the tasks you've described in the OP might well be classified as construction, but equally some might not!
Xavier123  
#21 Posted : 16 December 2014 16:47:32(UTC)
Rank: Super forum user
Xavier123

God bless us. Everyone. Back on topic, the mention of maintenance within both what IS and what IS NOT construction work is a little confusing. Never given it that much thought till now. First thoughts on reading through the ACoP and the Regs are thus: The key difference appears to be that which is being maintained. Structures and 'services' being maintained seem likely to fall under construction work. Fixed plant does not except in certain circumstances. The services bit seems vague since it includes mechanical, electrical, gas, etc. which makes me wonder what elements of 'fixed plant' they were trying to exclude within the ACoP...? I suspect the services bit thus relates to pipes, cabling etc. Am I getting that right? If so, following that logic might suggest that some of the tasks you've described in the OP might well be classified as construction, but equally some might not!
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.