Dear All,
As a fit-out contractor we are currently tendering for a project (not yet won).
The proposed start date for work on site is 28/04
As the Client has already appointed a CDM-C and the project, from the client's point of view, has already started, albeit no one is on site until April 28th, am I correct in thinking this project will proceed under CDM 2007 even though we won't start on site until after 6th April ? (End date proposed as end of June)
Cheers
Andy
|
|
|
|
Rank: Super forum user
|
It will not proceed under the 2007 regulations but will proceed under the 2015 regulations. Schedule 4. Although the duties are very similar they are not exactly the same.
|
|
|
|
Rank: Super forum user
|
From http://www.hse.gov.uk/co...m/regulation-changes.htm
"If the CDM co-ordinator has already been appointed, a principal designer must be appointed to replace the CDM co-ordinator by 6 October 2015, unless the project comes to an end before then.
In the period it takes to appoint the principal designer, the appointed CDM co-ordinator should comply with the duties contained in Schedule 4 to the new CDM 2015 Regulations. These duties reflect the existing requirements under CDM 2007 for the CDM co-ordinator rather than requiring CDM co-ordinators to act as principal designers, a role for which they may not be equipped."
|
|
|
|
Rank: Forum user
|
Thank you both,
Just re-read Schedule 4.
The CDM-C appointed by the Client is from a well known national property consultancy - So hopefully competent.
I'll make sure our commercial people understand the nuance of the transition.
Andy
|
|
|
|
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.