Hi all

I'm sure this is not the first time this has been asked but here goes!

Under CDM 2015 can a PD move into a PC role once the Pre construction phase has been completed? So in other words can they be the same individual/company

If this is the case then when appointing in writing can they be appointed both roles in one letter etc?

Cheers

Mike
Ron Hunter  
#2 Posted : 27 January 2016 15:56:18(UTC)
Rank: Super forum user
Ron Hunter

Yes, and often more efficient to be dual role, considering PC actions at the preconstruction phase if you have that luxury. Construction phase solutions can be agreed devised and consolidated very early on?
RayRapp  
#3 Posted : 27 January 2016 17:08:24(UTC)
Rank: Super forum user
RayRapp

As above, it can be done and indeed there are many good reasons why the PC and PD should be the same. It should be remebered that for BOTH roles the appointed need to be competent to carry out that specific role pursuant to CDM Regs 2015.

One letter can be used for appointing both roles.
mikecarr  
#4 Posted : 28 January 2016 09:17:02(UTC)
Rank: Forum user
mikecarr

Thank you both

I thought that was the case and it make life much easier!
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.