Can someone clarify the difference between Chapter 8 and the NRSWA, or are they used together.
|
|
|
|
Rank: Forum user
|
Chapert 8 is the pink book guide for road works NRSWA is the training required to do the work in simple terms
|
|
|
|
Rank: Super forum user
|
Briefly, NRSWA is a law (New Roads and Street Works Act 1991), and Chapter 8 is a Code of Practice. If your talking about works on the road (the Street Works part of NRSWA), then: The law says some general stuff about protection (eg works should be "adequately" guarded and lit), and like most codes of practice, Chapter 8 tries to assist with what the "adequately" part in that law means.
The Pink/Red book mentioned above is not Chapter 8, it's another code of practice, Safety at Street and Road Works, and compliance with this one is mandatory in England & Wales, unlike Chapter 8. You might find, though, that Chapter 8 compliance is a condition of your contract if you're working on roads.
The last one is smaller and simpler, and more aimed at local authority (ie non-trunk) roads. It can appear confusing to have different documents, and it can be (!) but people working with traffic management usually have a reasonable idea of what they need to do. That's a really simplified explanation of those terms - hope that's what you needed.
|
|
|
|
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.