My company are about to start Construction on a large building project right next to a canal and also will be carrying out some work on the exisiting piling sheets in place. Does anyone have any experience, procedures or guidance they could let me have to assist in writing a Construction Phase Plan?

Thanks in advane

georgiaredmayne  
#2 Posted : 04 December 2017 14:56:43(UTC)
Rank: Forum user
georgiaredmayne

Hi Dan,

I would start with looking at what activities will be taking place on site i.e.:

- Access and egress of plant and equipment near the canal.

- Is there a possibility of segregating that area so that people cannot physically get to the canal?

- Emergency plans for people who end up in the canal but first prevention of this.

- Induction to incorporate the fact that the canal is their and all of the above!

Georgia

RayRapp  
#3 Posted : 04 December 2017 15:03:33(UTC)
Rank: Super forum user
RayRapp

Need to be extra vigilant if using plant and machinery adjacent to water. Chocks and/or barriers will need to be installed and if working in MEWPS normally you would not wear a harness.

HSE guidance which may give you a starter for 10 - http://www.hse.gov.uk/ports/falls.htm

Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.