Rank: New forum user
|
Hi there, i am after confirmation on lifting plan requirements for the lifting of freight containers using 360 excavators and 17 meter forklift trucks.
Is an appointed person required to write a complex lift plan due to the bulk size of the items to be lifted (visual obstructions, etc)
or will a 'common schedule of lifts' suffice under the lifting equipment operators own supervision?
Many thanks.
|
|
|
|
Rank: Super forum user
|
Sorry when I first read this I thought the poster was looking for advice on a lifting plan or lifting of a freight container using a total of 360 excavators and 17, 1 metre high forklift trucks! Then I read it again! Sorry it’s Monday…
|
|
|
|