#1 Posted : 12 March 2002 09:01:00(UTC)
Rank: Guest
Admin

Posted By Bob Matthews Dear All, I have been asked to oversee the dismantling of some production lines at our UK site, which are then going to be re-assembled at our Greek site. I have been trying to devise a checklist for the staff in Greece to follow to ensure they assembly the lines safely and ensure no gets injured. (covering CDM, PAT testing, People & trucks etc) They will be assembling the lines among existing lines so there is the possibility of injury to production staff. I can oversee the lines in the UK, but it is difficult to ensure Greece will be safe. Am I on the right lines to do a check list for Greece to follow and sign when complete, or do you know of a better system? I doubt if I will be going to Greece but you never know, I might get lucky!!!!
Admin  
#2 Posted : 12 March 2002 09:02:00(UTC)
Rank: Guest
Admin

Posted By Bob Matthews Sorry I forgot to sign my name. Many thanks Bob Matthews
Admin  
#3 Posted : 12 March 2002 09:19:00(UTC)
Rank: Guest
Admin

Posted By Nick Higginson Bob, If you do have an accident take great care when filling in the F2508, as "slipped in Greece" may confuse the inspector. Sorry for the awful pun, Nick
Users browsing this topic
Guest (2)
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.