#1 Posted : 01 August 2005 16:40:00(UTC)
Rank: Guest
Admin

Posted By Simon Rider Asbestos Encapsulation I would like some sensible opinions on the matter of Asbestos encapsulation. I have come across a number of companies taking on the work of encapsulation recently painting asbestos boards with white paint. It is my opinion that painting white asbestos boards with whit paint makes identifying any damaged caused between each annul management inspection that much harder. What is the opinion of my fellow safety professionals out there, do you see any merit in encapsulating asbestos with a totally contrasting coloured paint (or Encapsulating product) to instantly show up any accidental damage or breakdown in material. Even more contentious should the HSE guidance be changed to cover this?
Admin  
#2 Posted : 01 August 2005 18:38:00(UTC)
Rank: Guest
Admin

Posted By TBC Encapsulation works if the material is sound and identified as to type etc. The only thing is, you have to keep a register on site, monitor at periods for damage or deterioration and ensure that anyone working in the area is aware of the location. Removal is obviously better in the long run, but this depends on the costs involved. Do your sums cost of removal versus the cost of encapsulation and all the hassles and added costs that involves. Other thoughts are bound to follow from our colleagues. Regards
Admin  
#3 Posted : 01 August 2005 18:40:00(UTC)
Rank: Guest
Admin

Posted By TBC Encapsulation is more than white paint by the way - a stronger rubbery solution is used.
Admin  
#4 Posted : 01 August 2005 23:12:00(UTC)
Rank: Guest
Admin

Posted By Dave Wilson If you follow HSE Guidance and undertake 'Asbestos Priority Risk Assessments' it should point you in the direction of what you need to do for all ACm on your premises. My opinion is that if it likely to get damaged and release fibres and people can then be exposed - remove, dont waste your time with encapsulation etc HSG 227 explains all, download foc from HSE
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.