Hi there,
Can anyone advise me on the recommended frequency for the inspection/testing of a generator (6kVa)used on a construction site?
|
|
|
|
Rank: Guest
|
Posted By Chris Pope
Three months is generally accepted from IEE and from HSG 141 available from HSE books
|
|
|
|