Rank: Guest
|
Posted By Crim Hi,
Sorry if I should know this, but how much notice is required to HSE before removing asbestos prior to demolition.
Thanks
|
|
|
|
Rank: Guest
|
Posted By holyterror72 It used to be via an ASB5 which (I think) was 14 days. Could be wrong though.
|
|
|
|
Rank: Guest
|
Posted By Crim Thanks Holy Terror - I think you are right, (I thought it was 10 working days but means the same)? Any other offers?
|
|
|
|
Rank: Guest
|
Posted By Bruce Sutherland 14 days and the powers that be have now decided that a day ceases at 1700 - so the days of getting the asb5 in by fax at 2355 to trigger the 14 days are now behind us
Bruce
|
|
|
|
Rank: Guest
|
Posted By Merlin Notification of work with asbestos 9. —(1) Subject to regulation 3(2), an employer shall not undertake any work with asbestos unless he has notified the appropriate office of the enforcing authority in writing of the particulars specified in Schedule 1 at least 14 days before commencing that work or such shorter time before as the enforcing authority may agree. (2) Where an employer has notified work in accordance with paragraph (1) and there is a material change in that work which might affect the particulars so notified (including the cessation of the work), the employer shall forthwith notify the appropriate office of the enforcing authority in writing of that change. follow the link to the control of asbestos regulations 2006 http://www.opsi.gov.uk/si/si2006/20062739.htm#9
|
|
|
|
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.