Posted By Robert S Woods Is all demolition work notifiable or does it need to meet the 30 days 500 hours criteria?
|
|
|
|
|
|
Rank: Guest
|
Posted By Robert K Lewis It needs to meet the criteria to be notified. But in reality the non-notifiable work still needs something similar to the CP Plan in any case.
Also there is a residual duty on the client to update the H&S File with the information from even non-notifiable work.
The real difference is therefore the CDMC involvement.
Bob
|
|
|
|
|
|
Rank: Guest
|
Posted By Ron Hunter CDM2007 Demolition no longer automatic notifiable (unless thresholds are reached) BUT all demolition required to have a written plan.
|
|
|
|
|
|
Rank: Guest
|
Posted By Ali Demolition is specficially excluded from Notification within CDM Regs, but you still require risk assessment and method statement. Ali
|
|
|
|
|
|
Rank: Guest
|
Posted By Crim Ali, "Demolition is specifically excluded from Notification within CDM Regs, but you still require risk assessment and method statement."
Where did you get that from?
The ACOP contains definitions of "not construction work" with no mention of demolition. Please check your facts.
|
|
|
|
|
|
Rank: Guest
|
Posted By Merlin Demolition or dismantling 29.—(1) The demolition or dismantling of a structure, or part of a structure, shall be planned and carried out in such a manner as to prevent danger or, where it is not practicable to prevent it, to reduce danger to as low a level as is reasonably practicable. (2) The arrangements for carrying out such demolition or dismantling shall be recorded in writing before the demolition or dismantling work begins.
It is notifiable under CDM once it reaches the threshold, the all or most of the regulations kick in Hope this helps
|
|
|
|
|
|
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.