Rank: Guest
|
Posted By Steve Hickey
Hi Can anyone help?
I'm looking to put together a fire risk assessment fro a timber frame building. I have considered all the usual risks but would like to know if anyone who has already carried out such a task has any other items they think I should be considering.
here are a list of the things I've considered
No Smoking
Training of fire wardens, identifiable HI Vis
designated fire points with rotary bell
waste segregation away from building
no hot work without a permit
all flammable liquids LPG to be stored in a fenced compound
specific fire induction
security against arson
electrical and gs supplies protected
PAT testing
material storage
many thanks
Steve
|
|
|
|
|
|
Rank: Guest
|
Posted By Mitch
Steve,
What is the building used for?
|
|
|
|
|
|
Rank: Guest
|
|
|
|
|
|
|
Rank: Guest
|
Posted By Steve Hickey
Thanks both
I have been in touch with the timber frame association and asked for some information i have also consulted the joint code of practice for prevention of fires on construction site and CIP H&S Manaual-blue book. to answer your question Mitch it is a timber frame building under construction. I just want to make sure I've ticked all the boxes
Steve
|
|
|
|
|
|
Rank: Guest
|
Posted By GeoffB4
I know Pudding Lane was a catastrophe but that was an exception.
Is a wooden framed building more likely to catch fire?
If the normal precautions are in place then is there a higher risk?
What additional precautions are needed if this is the case?
|
|
|
|
|
|
Rank: Guest
|
Posted By Ashley Wood
This is embarrassing as I am a fire consultant and never spotted it. 4 years ago I built a self build timber framed house. we nearly lost it because the electrical contractor had strung up some temporary lighting using 100 Watt bulbs. One of the bulbs was laying against a wood upright. The house is on 3 floors and the offending bulb was on the ground floor. The only people in the building at the time were 2 carpenters up on the 3rd floor. They smelt smoke and investigated. The heat from the bulb had charred its way through a 6 by 2 upright and was smoldering away nicely. As the guys reached it burst into flames. A kettle and a Co2 extinguisher were put to good use that day.
I gave myself a good talking to and fired myself as the project manager!
So, keep an eye on the temporary lighting.
|
|
|
|
|
|
Rank: Guest
|
Posted By Paul Bellis
You have mail!
Couple of issues within re maintaining fire integrity when constructing cavity barriers and sequencing works to protect the areas with plasterboard etc may be of use
Paul
|
|
|
|
|
|
Rank: Guest
|
|
|
|
|
|
|
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.