Does anybody have a copy of a Temporary Works procedure they could forward me? Thanks
grim72  
#2 Posted : 19 April 2010 12:53:15(UTC)
Rank: Super forum user
grim72

Not sure if this is what you are looking for?
http://www.dft.gov.uk/pg...manual/tsmchap8part1.pdf
montalban  
#3 Posted : 20 April 2010 06:55:53(UTC)
Rank: New forum user
montalban

hallam wrote:
Does anybody have a copy of a Temporary Works procedure they could forward me? Thanks


When you say temporary works, do you mean falsework/formwork type stuff?
Steve e ashton  
#4 Posted : 20 April 2010 11:07:04(UTC)
Rank: Super forum user
Steve e ashton

Hallam:

Have you seen / got access to the British Standard - BS 5975 2008 (Code of practice for temporary works procedures and the permissible stress design of falsework)? Whilst it doesn't have a 'procedure' it does set out recommended Management Arrangements which may meet your needs... (I only know this 'cos I'm currently looking at the document for the project I'm working on..)

Steve
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.