Trev B  
#1 Posted : 18 November 2020 20:27:50(UTC)
Rank: New forum user
Trev B

Hi, We have just had an H&S inspection by an external auditor and he advised the team that there are more stringent Temporary works requirement coming in soon. is this the case can anyone confirm or it is just more on the radar for the enforcement of current regulations? Thanks T

Edited by user 18 November 2020 20:30:10(UTC)  | Reason: Typos

sidestep45  
#2 Posted : 19 November 2020 12:00:59(UTC)
Rank: Forum user
sidestep45

If there are this is a good place to look

https://www.twforum.org.uk/home

peter gotch  
#3 Posted : 19 November 2020 12:31:42(UTC)
Rank: Super forum user
peter gotch

Trev

Suspect your auditor is looking at the proposals for more effective Building Regulations inclusive of a new Building Regulator under the Health and Safety Executive.

Arguably this will have more impact on Permanent Works than TW, though clearly if you design in flammable cladding into a tower block then this presents temporary as well as ongoing risks.

Of the VERY, VERY small number of prosecutions against Designers, CDM Co-ordinators and Principal Designers under the CDM Regulations, a couple have involved lack of control of the fire risks associated with timber frame construction in extensions to occupied residential care homes.

Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.