If a lift Crane lift is planned and it involves a suspended man basket; does the crane require a seperate 6 monthly inspection (as it now becomes equipment used for lifting personnel) or if the 12 monthly crane cert is only 5 months old is this acceptable. When reading the Loler regs I interpret it as the crane becomes equipment for lifting personnel as soon as the man basket is attached, however it also states that cranes require a 12 monthly inspection. Has anyone got definitive experience of this situation and suitable advice.
|
|
|
|
Rank: Forum user
|
The crane requires to be within 6 months of its previous examination. There should not be a need for a separate certificate.
The man-riding basket will be subject to 6 monthly as standard.
|
1 user thanked arnoldisnumerouno for this useful post.
|
|
|
Rank: New forum user
|
Thanks for your swift reply, most helpful.
|
|
|
|
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.