Welcome Guest! The IOSH forums are a free resource to both members and non-members. Login or register to use them

Postings made by forum users are personal opinions. IOSH is not responsible for the content or accuracy of any of the information contained in forum postings. Please carefully consider any advice you receive.

Notification

Icon
Error

Options
Go to last post Go to first unread
cmarshall1983@outlook.com  
#1 Posted : 11 May 2023 13:43:34(UTC)
Rank: Forum user
cmarshall1983@outlook.com

Afternoon All,

The company I work for is looking to take on a new project which will involve removing up to 6000 litres of Diesel before working on the vehicles. 

Previously we would have a company come on site and drain them for us, however for this project we will be replacing the fuel after completing works.

The question has been asked if we can store the Diesel on site, it will be in IBC's and also a large Flam Cabinet, reading online over 3500litres could require authorisation from local council, has anyone had anything similar? 

Thanks in advance. 

Roundtuit  
#2 Posted : 11 May 2023 18:41:55(UTC)
Rank: Super forum user
Roundtuit

Presumably this project will not involve the simultaneous arrival and draining prior to works.

Therefore as an alternative to huge diesel storage have the first "batch" arrive next to empty (including using vehicles that will remain on the road as additional receivers for significant excess) then as each new batch arrives transfer their diesel to the departing completed vehicles.

That way (barring transfer bund spillage) you have no storage requirement as all diesel will be in vehicle tanks.

Roundtuit  
#3 Posted : 11 May 2023 18:41:55(UTC)
Rank: Super forum user
Roundtuit

Presumably this project will not involve the simultaneous arrival and draining prior to works.

Therefore as an alternative to huge diesel storage have the first "batch" arrive next to empty (including using vehicles that will remain on the road as additional receivers for significant excess) then as each new batch arrives transfer their diesel to the departing completed vehicles.

That way (barring transfer bund spillage) you have no storage requirement as all diesel will be in vehicle tanks.

cmarshall1983@outlook.com  
#4 Posted : 15 May 2023 08:00:21(UTC)
Rank: Forum user
cmarshall1983@outlook.com

Originally Posted by: Roundtuit Go to Quoted Post

Presumably this project will not involve the simultaneous arrival and draining prior to works.

Therefore as an alternative to huge diesel storage have the first "batch" arrive next to empty (including using vehicles that will remain on the road as additional receivers for significant excess) then as each new batch arrives transfer their diesel to the departing completed vehicles.

That way (barring transfer bund spillage) you have no storage requirement as all diesel will be in vehicle tanks.

Hey thanks for the pointer, however they are trains, so if they are delivered close to empty it may cause some major issues if they run out on route. 

peter gotch  
#5 Posted : 15 May 2023 09:59:17(UTC)
Rank: Super forum user
peter gotch

CM, OK it's trains rather than road vehicles but the principle offered by Roundtuit could still work.

So, if you are doing maintenance for a Train Operating Company (whether passenger and/or freight) you could probably quite easily agree with the TOC that they will deliver rolling stock such that the fuel tank is far from full - just like a car a train comes with a fuel gauge!!

So, you could apply the first principle of managing health and safety - remove the hazard or at least a substantial part of it.

Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.