Hi Learned Friends,
I have always been of the understanding that from – BS 5266 2005 it states the following regarding a 6 monthly test which it states its by a competent person:
• Daily Test – A visual inspection to identify the system is in a ready condition and does not require a test operation (i.e. Charge lights functional, Maintained luminaries operational)
• Monthly Test – A functional test (i.e. flick lights on to confirm operation)
• 6 Monthly Test – 3 Hour rated luminaries tested for 1 hour and 1 hour rated luminaries tested for 15 minutes.
• Annually – Full duration test (i.e. 3 hour, 1 hour tests)
I have now been informed by a contractor stating he has been on a recent refresher course that the 6 month test is no longer required just an Annual one. Is anyone else aware of this and how often does everyone else have them maintained?
Thanks In advance
Alan
|
|
|
|
Rank: Guest
|
I believe that he is correct, although there may be some exceptions depending upon the nature of the premises.
I have agreements to have the emergency lighting serviced/ tested every 6 months as per BS 5266 in all of our branches. However, the lighting is serviced by the same company that services our fire alarm systems and I've negotiated a deal whereby the lighting is serviced at no extra cost, so it makes sense (for me, at least) to keep to the existing schedule.
|
|
|
|
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.