Quick question for the folk with cdm knowledge?
If there is a requirement to move 1000s of tons of earth that would last more than 8 weeks - would this fall under cdm (notifiable)?
It would involve diggers and a lot of trucks.
Sorry if its a simple one but I need to ask?
Thanks you.
|
|
|
|
Rank: Super forum user
|
More info please; as in agriculture, quarrying and similar areas movement of large amounts of earth are regularly undertaken but they are not classed as CDM areas because they have no proximity to a construction activity
|
|
|
|
Rank: Forum user
|
Thanks Bob - I think you have given me what I need - no construction works - just a massive pile left on a site.
|
|
|
|
Rank: Super forum user
|
Sounds painful
(Sorry just couldn't resist).
|
|
|
|
Rank: Forum user
|
When you say "site" what exactly is the site. If the earth was part of a construction or demolition process then it should have been removed within the time as specified on the F10, there is flexibility there however.
If a F10 was issued initially then this will need to be extended.
Simplest question to answer is why has the material been excavated/stockpiled? The answer to this quetion will determine what you need to do.
|
|
|
|
Rank: Super forum user
|
Similarly,
Is this removal in preparation for something else (site clearance)?
|
|
|
|
Rank: Forum user
|
The EA might be interested too, my mate had a job where he moved a lot of earth, SEPA stopped the job as they said they were changing the way water would run off site and could potentially divert water to residential areas if it were to rain heavily / flood. Just food for thought.
|
|
|
|
Rank: Super forum user
|
You may find this Act of interest, or maybe not.
Agricultural Land (Removal of Surface Soil) Act 1953
|
|
|
|
Rank: Super forum user
|
You will need to prove no contamination if it is to go for recycling or other disposal that is not on a hazardous waste site
Bob
|
|
|
|
Rank: Super forum user
|
You could just proceed on the basis that it is Construction and Notify. You need not make any specialist appointment, CDM-C role defaults to the Client where no appointment is made. Presumably there is no "design" or Designer involvement.
The work will require welfare provision, there will no doubt be various site-specific issues requiring consideration and methodology and your will need a competent contractor to be in overall charge (the Principal Contractor). If your Organisation is a "contractor" then you can also assume the role of the Principal Contractor.
You're probably aware that the facility exists to Notify on-line via HSE website and that the CDM ACoP L144 is available as a free pdf from HSE website too.
Appendices 2 and 3 of the ACoP (pages 101 - 107) should serve as a useful initial focus.
|
|
|
|
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.