#1 Posted : 16 June 2015 10:18:33(UTC)
Rank: Forum user
mikecarr

Hi all

just trying the get my heaed around this.

Can a PD & PC be the same person, company, etc if there is only one contractor invloved in a project?.

cheers

jay  
#2 Posted : 16 June 2015 10:29:53(UTC)
Rank: Super forum user
jay

No need to appoint PC or PD if there is only one contractor, unless "3" below applies, i.e. it is a notifiable prohect.

Key changes of the new CDM Regulations 2015—CITB infographic version

http://www.citb.co.uk/do...ographic%20-%20final.pdf

1. All projects must have:
• workers with the right skills, knowledge, training and experience
• contractors providing appropriate supervision, instruction and information
• a written construction phase plan

2. Project where more than one contractor is involved (domestic or non-domestic) must have 1 above plus:
• principal designer and principal contractor must be appointed
• a health and safety file


3. If work is scheduled to:
• last longer than 30 working days and
• have more than 20 workers working simultaneously at any point in the project
• OR exceeds 500 person days
All of 1 and 2 above plus
• Client must notify project to HSE
achrn  
#3 Posted : 16 June 2015 10:35:59(UTC)
Rank: Super forum user
achrn

Jay wrote:
No need to appoint PC or PD if there is only one contractor, unless "3" below applies, i.e. it is a notifiable prohect.


No PC or PD if there is only one contractor full stop. That is, it's irrelevant whether it's notifiable or not.

However, if there is more than one contractor, the same party can be both PC and PD.
ashleywillson  
#4 Posted : 16 June 2015 10:43:35(UTC)
Rank: Super forum user
ashleywillson

Agree with achrn on this.

Notification and appointment of duty holders are two different things but it can get confusing...

Mikecarr - achrn has answered your question. BUT if it was a site with multiple contractors, as long as the single person, company etc is competent then as far as I am aware they would be able to hold multiple duties. Certainly for a company, think about a large construction company that may have a "design" department and a "construction management" department. Easy to hold 2 duties in that vein.
mikecarr  
#5 Posted : 17 June 2015 11:43:51(UTC)
Rank: Forum user
mikecarr

Thanks all for your help!
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.