Welcome Guest! The IOSH forums are a free resource to both members and non-members. Login or register to use them

Postings made by forum users are personal opinions. IOSH is not responsible for the content or accuracy of any of the information contained in forum postings. Please carefully consider any advice you receive.

Notification

Icon
Error

Options
Go to last post Go to first unread
Redders  
#1 Posted : 18 May 2016 15:12:33(UTC)
Rank: Forum user
Redders

Is anyone aware of the required retention times for the various records and documentation following the completion of the project?
MEden380  
#2 Posted : 19 May 2016 13:56:39(UTC)
Rank: Super forum user
MEden380

A question in the latest CSCS health & safety test.
Scaffold inspections
Temporary works inspections
Excavation work inspections
Should be kept on site for the length of the project and for three months after the project is completed
achrn  
#3 Posted : 19 May 2016 14:17:24(UTC)
Rank: Super forum user
achrn

MEden380 wrote:
A question in the latest CSCS health & safety test.
Scaffold inspections
Temporary works inspections
Excavation work inspections
Should be kept on site for the length of the project and for three months after the project is completed


It has been in the test for a few years. This is the first year they've got the answer right though.

However, that's only with reference to the requirements of the CDM regs. There may be other requirements requiring retention of these (or other records) for longer. I think the question needs to be more specific - our insurers (for example) require that we retain some records for longer than that, and then there are records like certain asbestos work which should be kept for 40 years (I think - we don't do asbestos work).
Redders  
#4 Posted : 19 May 2016 16:34:21(UTC)
Rank: Forum user
Redders

You're right about the question being a bit vague achrn, what I mean is everything from the tendering phase through to handing over the H&S File to the client and packing up the site. I suppose there would be financial and legal regulatory requirements. Anyway, does anyone have any guidance on this?
Ron Hunter  
#5 Posted : 19 May 2016 17:32:07(UTC)
Rank: Super forum user
Ron Hunter

MEden380 wrote:
A question in the latest CSCS health & safety test.
Scaffold inspections
Temporary works inspections
Excavation work inspections
Should be kept on site for the length of the project and for three months after the project is completed



Can someone point to the stipulated requirement for temporary works record retention please?

CDM refers to excavations, cofferdams and caissons.
WAHR refers to scaffold from which a person could fall 2 metres or more.
achrn  
#6 Posted : 20 May 2016 08:38:00(UTC)
Rank: Super forum user
achrn

Ron Hunter wrote:

Can someone point to the stipulated requirement for temporary works record retention please?

CDM refers to excavations, cofferdams and caissons.
WAHR refers to scaffold from which a person could fall 2 metres or more.


I read it as meaning retention of temporary works inspection records where there is a requirement for such inspections, not as being that all temporary works need inspection (which I think is obviously not the case, if you adopt a broad definition of temporary works).

However, I didn't check the CDM regs before posting and I agree the CDM regs do not mandate a retention period for such records.

Returning to the original question, I don't think I'm even going to try to list all the potential retention periods for every potential record in every potential project. The question does not even constrain it to a particular sort of project (the answers to date have assumed we're talking construction project, but the question doesn't say that) or whether we're talking only statute requirements, or guidance, or such things as insurers requiring records retention. I've never seen any attempt to assemble such a list.
Ian Bell2  
#7 Posted : 20 May 2016 09:22:45(UTC)
Rank: Super forum user
Ian Bell2

As regards main project/construction design documents - as others have said there is no stipulation in CDM. So its down to company policy. Most companies I have worked for retain design document for the expected design life of the facility.

In the oil & gas industry this is typically 25 or 30yrs.
firesafety101  
#8 Posted : 20 May 2016 10:03:44(UTC)
Rank: Super forum user
firesafety101

Redders, thank you for asking the question.

As self employed I have kept various records for many many years, risk assessment, construction safety records, site inspection etc. etc.

They are all in my shed which I am replacing next month.

I will now get rid of them all.

Is it OK to skip them I wonder.
Redders  
#9 Posted : 23 May 2016 15:19:05(UTC)
Rank: Forum user
Redders

Found a useful guidance document from the IRMS:
http://www.irms.org.uk/i...th_and_Safety_Records_UK


MEden380  
#10 Posted : 24 May 2016 09:17:05(UTC)
Rank: Super forum user
MEden380

For information CDM Regulations 2015
Regulation 24
Para (3) The person on whose behalf the inspection was carried out must—
(a) keep the report or a copy of it available for inspection by an inspector for the Executive—
(i) at the site where the inspection was carried out until the
construction work is completed; and
(ii) after that for 3 months; and
(b) send to the inspector such extracts from or copies of the report as the inspector may from time to time require.
Users browsing this topic
Guest
You cannot post new topics in this forum.
You cannot reply to topics in this forum.
You cannot delete your posts in this forum.
You cannot edit your posts in this forum.
You cannot create polls in this forum.
You cannot vote in polls in this forum.